The first units of a battery energy storage system (BESS) have arrived at European Energy’s operational Mokoan solar PV plant in northern Victoria, Australia.
European Energy Australia, the local subsidiary of the Denmark-headquartered renewable energy developer, said on Wednesday (25 November) that six BESS units, each weighing about 36 tonnes, were delivered that morning and craned into place by its construction team.
The company called the delivery “an early Christmas present” that was “exactly what we asked for”. It said more units will be delivered over the next week or so, and that the completed BESS will be sized at 88MWh.
That is higher than the 40MW/80MWh figure European Energy gave in July, when the company reached financial close on the Mokoan solar-plus-storage project with an AU$110 million (US$72.5 million) non-recourse package from Deutsche Bank.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
The package refinanced the existing solar PV plant and funded construction of the AC-coupled BESS. Catriona McLeod, managing director of European Energy Australia, called the financing “an important milestone for our Australian portfolio” at the time.
The Mokoan site covers 94 hectares about 25km south-west of Wangaratta. Its 58MW solar PV plant has been fully operational since June 2025 and is expected to generate about 113GWh a year.
European Energy acquired the project from Lightsource bp in December 2022 and began construction in the first half of 2024. In March 2025, PV Tech reported that Mokoan had become European Energy’s first commissioned solar PV plant in Australia, initially financed by NORD/LB’s Singapore branch under green loan principles.
The project was selected in the first tender of the Capacity Investment Scheme (CIS), the federal government’s revenue underwriting programme. That round, which sought 6GW of generation, awarded 2.75GW of solar PV and 3.55GW of wind across 19 projects in December 2024.
Mokoan also features in Amazon’s Australian renewable energy procurement. The technology company listed the Mokoan Solar Farm Battery among nine power purchase agreements (PPAs) signed to support its Australian data centre expansion, alongside projects from OX2, X-ELIO, Anza and TagEnergy.
Storage added to Victoria’s operating solar PV plants
European Energy is also building the Winton North solar-plus-storage project, about 22km south-west of Wangaratta. In September, PV Tech reported that all 200,172 solar modules had been installed at the 131MW site, with a 100MW BESS to follow.
Amazon has since signed a PPA for the Winton North BESS, adding to its existing solar PV offtake from the project. Spanish manufacturer Ingeteam is supplying inverters and control systems for both phases under a contract signed in October 2025.
Other operating solar PV plants in the region are adding storage too. Victoria’s State Electricity Commission (SEC) recently signed a 10-year offtake covering the nearby Glenrowan Solar Farm and a planned 102MW, 4-hour BESS at the site.
Across the National Electricity Market (NEM), 2.4GW of existing solar projects began or completed processes to add a BESS in the 2026 financial year, according to the Australian Energy Market Operator (AEMO). That was the same year Australia added a record 9.1GW of new generation and storage to the NEM, more than double the previous year.
AEMO’s latest Summer Outlook found that BESS account for 5.3GW of the 8.4GW of new capacity added to the NEM since December 2025. Earlier this month, energy held across the NEM’s BESS fleet reached a record 20.17GWh, up 203% in a year.
The latest Institute for Energy Economics and Financial Analysis (IEEFA) scorecard said the remaining utility-scale BESS gap to 2030 could be in construction within 18 months at the current rate.
Never miss an Australian energy storage story. Sign up for our Australia newsletter and get the latest project announcements, policy updates and market analysis delivered directly to you.