
Hamburg-based independent power producer (IPP) Blue Elephant Energy has acquired a 95% stake in a 40MW/160MWh battery energy storage system (BESS) project in the Netherlands from developer TPSolar.
The 4-hour BESS Zuidvelde, announced on Thursday (26 November), is Blue Elephant Energy’s first BESS in the Dutch market. It will be built on the site of the existing Zuidvelde solar PV plant in the municipality of Noordenveld, in the northern Dutch province of Drenthe.
Under a cable pooling agreement, the BESS and the solar PV plant will share the existing grid connection, so the project does not need a new one. Blue Elephant Energy said this is an advantage in the Netherlands, where grid congestion has become a major bottleneck for new projects.
TPSolar will manage construction, which is due to start in the first quarter of 2027, and will take over maintenance once the BESS is operating. Commissioning is scheduled for the third quarter of 2027.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
ING Netherlands is financing the project, having also financed the neighbouring Zuidvelde solar PV plant.
The bank provided project finance for Return’s 100MW/200MWh Antares project in Waddinxveen, which Energy-Storage.news reported in October had become the largest BESS to reach commercial operation in the Netherlands, using technology from Dutch firm Alfen.
“BESS Zuidvelde is our entry into the Dutch battery storage market,” said Tim Kallas, chief investment officer at Blue Elephant Energy.
“It’s exactly how we believe it should be done: right inside an existing solar park, using grid capacity that is already there.”
Kallas said solar and storage “belong together” and that the company plans to bring battery storage to further sites across its portfolio.
Connor Hendriks, director of battery energy storage systems at TPSolar, said Zuidvelde is the company’s largest storage project to date.
“Energy storage plays a key role in alleviating grid congestion, improving security of supply and reducing the overall costs of the energy transition,” Hendriks said.
Gino Schuur, head of sustainable finance at ING Business Banking NL, said the project “shows how battery storage can combine renewable energy, flexibility and smarter use of existing grid infrastructure”.
The deal extends an existing relationship between the two companies. Kallas said the project “builds on the trust we have established across several joint projects”, and Blue Elephant Energy’s website lists a 95% stake in the 49.75MW Zuidvelde solar PV plant, held since 2024.
TPSolar, a family-run developer founded in 2015, signed an agreement with Chinese manufacturer AIKO in May 2025 to supply 50MW of back contact solar modules for Zuidvelde. TPSolar has built and manages 11 solar PV plants in which it remains a co-owner, and said its portfolio of solar projects and co-located BESS exceeds 800MW.
Blue Elephant Energy, founded in 2016, develops, acquires and operates solar PV, onshore wind and BESS projects. It has a 2.4GW portfolio in operation and under construction across eight countries, focused on Germany and the Netherlands, and a pipeline of more than 10GW.
In June 2025, the company secured a €200 million (US$214 million) investment from Infranity to fund the development and construction of a 1GW renewables pipeline across Europe. At that time, 717MWp of its installed solar PV capacity was in the Netherlands.
Co-location as a route around Dutch grid congestion
Adding BESS at solar PV sites has been used in the Netherlands to avoid long waits for new grid capacity.
In 2023, Energy-Storage.news reported that developer PowerField had found a way around Dutch grid congestion with BESS at solar PV plants, including a 12MWh system at Emmen, also in Drenthe, that would otherwise not have connected until 2028.
Last week, Statkraft signed a 10-year agreement with Ampyr Solar Europe that pairs a PPA with a part-tolled, part-merchant BESS contract at the Snelle Loop project in North Brabant, which combines 27MW of solar PV with a 10MW/40MWh BESS.
Merchant exposure for co-located assets in the Netherlands is shaped by volatile imbalance prices.
In a guest article for Energy-Storage.news, Powerlys founder Omer Bumin set out what six months of Dutch market data showed about dispatch optimisation for a hybrid asset with a 5MW/10MWh BESS.
Over the first 79 days, the short imbalance price averaged €118/MWh and ranged from -€1,656/MWh to €3,981/MWh.
Transmission system operator (TSO) TenneT said in 2023 that the Netherlands needs 9GW of large-scale BESS connected to its grid by 2030, and warned that new storage should not add to grid congestion.
Larger standalone projects are also under way. Return and Vopak are each building 800MWh BESS in the Netherlands, while Giga Storage and RWE have projects of more than 1GWh under construction.