NYSE-listed energy infrastructure company Energy Vault has reported its Q3 2026 financial results and the close of non-recourse project financing for its 150MW/300MWh SOSA Energy Centre in Texas, US.
Q3 2026 financial results
The battery energy storage system (BESS) and ESS company said its backlog reached US$2.3 billion as of 10 November 2026, up 15% sequentially and 147% year-on-year, comprising roughly US$800 million in build-and-transfer backlog and US$1.5 billion in build-own-and-operate backlog.
Q3 2026 revenue came in at US$13.1 million, in line with consensus estimates but down 61% year-on-year, which the company attributed to the timing of planned project deliveries.
GAAP gross margin was 71% and adjusted gross margin was 81.1%; excluding the benefit of US$4.3 million in tariff refunds, these margins were 37.9% and 48%, respectively.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
GAAP net loss for the quarter was approximately US$28.2 million, compared with US$26.8 million in the prior-year period, while adjusted EBITDA was a loss of US$14.7 million, against a US$6 million loss a year earlier.
Total cash, including restricted cash, rose to US$236 million as of 30 September 2026, up 59% sequentially and 281% year-on-year, exceeding the company’s expectations. Corporate-level recourse debt declined by US$12 million sequentially.
The company affirmed full-year 2026 revenue guidance of US$290–310 million, at the top half of its previous range, and issued preliminary 2027 guidance of US$600–700 million in revenue and US$40–50 million in adjusted EBITDA.
This builds on the company’s full-year 2025 results, released in March 2026, which showed revenue of US$203.7 million, a 340% increase on the prior year’s US$46.2 million, driven by growth in Australian ESS projects and initial revenue from Asset Vault, Energy Vault’s wholly owned subsidiary dedicated to developing, constructing, owning, and managing energy storage assets worldwide.
At that time, the company projected 2026 revenue of US$225–300 million, a range it has now narrowed and lifted to the upper half with its latest guidance.
SOSA Energy Centre financing
Energy Vault also recently announced the close of US$78 million in construction and bridge financing for the SOSA Energy Centre, its 150MW/300MWh BESS in Madison County, Texas.
The company stated that the bridge financing will be repaid upon completion with an already committed US$80 million preferred equity investment, with an additional draw on the company’s existing OIC preferred facility to fund the incremental equity required.
SOSA was the first asset formally acquired under Asset Vault. The project was originally developed by Shell subsidiary Savion and was acquired by Energy Vault in October 2025, at the time supported by a US$300 million preferred equity investment from North American infrastructure investor OIC.
Construction began in Q4 2025, with civil works now complete and a substation installed; Energy Vault is self-performing engineering, procurement and construction (EPC), with major equipment expected on site in the coming months.
Commercial operation is expected in Q3 2027, slightly later than the Q1 2027 timeline originally indicated, with the project set to operate on a merchant basis in the Electricity Reliability Council of Texas (ERCOT) North market, retaining flexibility to enter a contracted offtake agreement as conditions evolve.
Energy Vault claimed that SOSA represents an estimated US$100 million investment in Madison County and is expected to generate US$9.3 million in tax revenue for North Zulch Independent School District and the county over ten years, while supporting 65 local construction jobs.
Over its life, the project is expected to deliver US$250–300 million-plus in long-term revenues at EBITDA margins of 65–75%, consistent with other Asset Vault portfolio projects.
Wider portfolio and AI infrastructure push
The SOSA financing sits within a broader period of expansion for Energy Vault across both its energy storage and AI infrastructure businesses.
In September 2026, the company closed its second portfolio acquisition of the year, acquiring 2.3GW of US BESS development projects, including 350MW ready-to-build, from Goshe Energy Storage, backed by a US$40 million credit facility from S2G Investments.
This followed an earlier 2026 acquisition of a Japanese BESS portfolio from Baywa Renewables.
In Australia, Energy Vault received formal grid interconnection approval for its 125MW/1GWh Stoney Creek BESS in New South Wales, having already secured project land and state development approval, paving the way for construction to ramp up. Multiple project financings in both the US and Australia remain underway.
On the AI infrastructure side, Energy Vault received a US$137.5 million senior secured credit facility from Eagle Point Credit Management in October 2026 to support procurement of 275MW of reciprocating engine generation capacity using Rolls-Royce MTU technology, with equipment deliveries expected from the second half of 2027 through the first half of 2028.
The company also advanced the development of its Digital Vault Sulcis in Sardinia, Italy, following its designation as a project of pre-eminent national strategic interest.