RWE and Giga Storage move to construction on gigawatt-hour Netherlands and Belgium batteries

LinkedIn
Twitter
Reddit
Facebook
Email

RWE has taken a final investment decision (FID) on 400MW/1.1GWh BESS in the Netherlands with construction to start in due course, while Giga Storage has started building its 2.8GWh Green Turtle project in Belgium. Both are set to be commissioned in early 2028.

RWE to build congestion-relieving BESS in Netherlands

Power firm RWE has taken FID on the 2.75-hour battery energy storage system (BESS) to be built at the Moerdijk power station site, it said yesterday (21 September).

Commissioning is planned for the second quarter of 2028, and it will contribute to the system integration of the 795MW OranjeWind offshore project, which is a joint venture between RWE and TotalEnergies. The BESS will comprise 208 lithium-ion containers (a little over 5MWh each)

Mark Lentjes, regional director of grid operator TenneT Southern Netherland said the BESS would act as a congestion reliever. It will do this via ‘steering agreements’ with TenneT, whereby it will be dispatched to relieve congestion in the Noord-Brabant region. That means that space can be created on the grid for parties on the waiting list.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

It is not the first such project in the Netherlands; we reported on one earlier this year. Other projects have been given ‘time-dependent transport rights’ (TDTR), similar to a flexible connection agreement (FCA) in Germany

The Moerdijk benefits from a location close to the 150,000V high-voltage substation at Moerdijk-Noord, where it will help to alleviate the regional bottleneck, which in turn has an impact on congestion across the whole region, Lentjes said. The project can also provide advanced grid services such as instantaneous reserve (inertia).

RWE is highly active in BESS in the Netherlands, its home country of Germany as well as the US and Australia, see all coverage of it here.

Giga Storage starts building Belgium’s largest BESS project

BESS owner-operator Giga Storage has launched construction on its Green Turtle project, a 700MW/2,800MWh system, one of the largest in Europe.

Announced last week (17 September), the start of construction comes a few months after financing was secured and a letter of intent (LOI) was agreed with Tesla to supply the project.

Tesla will provide 640 of its lithium iron phosphate-based (LFP) Megapack 3 BESS units under a full EPC wrap contract, while civil works are being carried out by Stadbader Contractors. We did a deep-dive on the Megapack 3 product in a recent ESN Premium article.

Commissioning is scheduled for March 2028. Preparatory earthworks and roadworks commenced in mid-August and now the batteries, cabling, and high-voltage installations will begin.

Like RWE’s Dutch project, Green Turtle benefits from close proximity to a high-voltage line, the 380kV Van Eyck-Gramme line. Grid operator Elia is building a new high-voltage substation at the site to accommodate the project.

Giga Storage, owned by investor InfraVia since 2024, is based in the Netherlands and also is active there, recently launching construction on a 1.2GWh BESS there last year, and it is also building a 1.4GWh one in Germany.

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

September 22, 2026
Covenergo and Delta Capacity have begun construction on AKKU One, a standalone 125MW/300MWh battery energy storage system (BESS) in Lapinlahti, Finland, with commissioning targeted for the fourth quarter of 2027.
September 17, 2026
The transition of battery energy storage systems (BESS) from development to operations remains fraught with technical gaps and communication breakdowns.
September 15, 2026
BESS project owners, lenders and optimisers kicked off the Energy Storage Summit Germany 2026 today in Berlin with a discussion on developing a bankable project.
Premium
September 15, 2026
A regulatory change is opening Germany’s energy markets to 23GWh of home batteries. The co-CEO of VPP platform Flexa discusses what it could mean for the market.
September 14, 2026
We hear from the BESS lead at RWE Renewables Europe & Australia ahead of the Energy Storage Summit Germany 2026, discussing the major trends, challenges and opportunities in the country’s grid-scale storage market.