Owner-operator Giga Storage has secured a €450 million (US$512 million) financing package for its 700MW/2,800MWh Green Turtle BESS project in Belgium.
The company announced the debt financing from a consortium of 10 banks last week (10 July). They are ABN AMRO Bank N.V., Belfius, SMBC Group, Rabobank, ING, Hamburg Commercial Bank, Santander, Triodos Bank and Triodos Investment Management.
The remaining equity will be provided by infrastructure investor InfraVia Capital Partners, which acquired Giga in 2024. The Green Turtle project has come a little later than expected, with the company telling us at the time that it expected to start construction that year. But it was a project of an unprecedented size in Europe at the time, so delays are not out of the ordinary.
Construction will start in September this year at the Rotem industrial estate in Dilsen-Stokkem, which has a direct connection to TSO Elia’s 380kV high voltage grid. The project is expected to come online in 2028, when it will be among the largest in Europe.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
Tesla is providing its Megapack battery energy storage system (BESS) as well as engineering, procurement and construction (EPC) services, in a deal announced at last month’s Intersolar Europe.
Kevin Dijkers, CEO of Giga Storage, said: “Green Turtle is much more than an energy storage project. It is critical infrastructure that strengthens Belgium’s security of supply, enables more renewable energy, and reduces dependence on imported fossil fuels.”
The company is based in the Netherlands but first embarked on its larger projects in neighbouring Belgium, where there is a more storage-friendly regulatory regime and less severe grid connection restraints, such as reduced grid fees, along with a capacity market (CM).
However, it did launch construction on a 1.2GWh BESS in the Netherlands last year, and is building a 1.4GWh one in Germany too.
We’ve previously interviewed Giga Storage’s then-CEO Ruud Nijs in 2022 and its then-CCO Lars Rupert in 2024.