Giga Storage secures finance for 2.8GWh ‘critical infrastructure’ Belgium BESS

LinkedIn
Twitter
Reddit
Facebook
Email

Owner-operator Giga Storage has secured a €450 million (US$512 million) financing package for its 700MW/2,800MWh Green Turtle BESS project in Belgium.

The company announced the debt financing from a consortium of 10 banks last week (10 July). They are ABN AMRO Bank N.V., Belfius, SMBC Group, Rabobank, ING, Hamburg Commercial Bank, Santander, Triodos Bank and Triodos Investment Management.

The remaining equity will be provided by infrastructure investor InfraVia Capital Partners, which acquired Giga in 2024. The Green Turtle project has come a little later than expected, with the company telling us at the time that it expected to start construction that year. But it was a project of an unprecedented size in Europe at the time, so delays are not out of the ordinary.

Construction will start in September this year at the Rotem industrial estate in Dilsen-Stokkem, which has a direct connection to TSO Elia’s 380kV high voltage grid. The project is expected to come online in 2028, when it will be among the largest in Europe.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Tesla is providing its Megapack battery energy storage system (BESS) as well as engineering, procurement and construction (EPC) services, in a deal announced at last month’s Intersolar Europe.

Kevin Dijkers, CEO of Giga Storage, said: “Green Turtle is much more than an energy storage project. It is critical infrastructure that strengthens Belgium’s security of supply, enables more renewable energy, and reduces dependence on imported fossil fuels.”

The company is based in the Netherlands but first embarked on its larger projects in neighbouring Belgium, where there is a more storage-friendly regulatory regime and less severe grid connection restraints, such as reduced grid fees, along with a capacity market (CM).

However, it did launch construction on a 1.2GWh BESS in the Netherlands last year, and is building a 1.4GWh one in Germany too.

We’ve previously interviewed Giga Storage’s then-CEO Ruud Nijs in 2022 and its then-CCO Lars Rupert in 2024.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.
2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

October 23, 2026
Tesla’s energy storage business deployed 13.7GWh in Q3 2026, its second-highest quarterly figure to date, but saw a 16% year-on-year decline in revenues for the division.
October 22, 2026
As demand for battery storage soars, the European Union (EU) has tried to grow its local battery supply chain with mixed success so far, writes PV ESS analyst Charlotte Gisbourne.
Premium
October 22, 2026
BESS investments in the French market are moving to longer durations with saturation expected to hit the secondary reserve market, currently the main way operational projects make their money.
October 22, 2026
IPP and EPC Faria Renewables has inaugurated its 49.9MW/134.16MWh Galani BESS project in Elassona, Greece.
October 21, 2026
German IPP Enertrag and Swiss utility Axpo have launched BESS projects in France, including what could be the country’s first 3-hour project.