Australian renewables developer Maoneng reveals details of proposed 240MW / 480MWh battery project

LinkedIn
Twitter
Reddit
Facebook
Email
Rendering of how the 480MWh Mornington BESS project would look. Image: Maoneng.

Renewable energy company Maoneng has made public its plans for a 240MWp / 480MWh battery energy storage system (BESS) which it has proposed to build in Victoria, Australia.

The standalone BESS would be built in Victoria’s Mornington Peninsula, an area subject to fluctuations in demand for power due largely to seasonal tourism. The company said this morning in a press release emailed to Energy-Storage.news that details of the project, which would also aid local electric system reliability and aid the integration of renewable energy on the network, have gone on public exhibition.

A competitive tender process is underway to find a contractor to work on the project, which will be connected to an existing substation and could create 150 jobs during its 12-month construction phase.

According to figures from the Australian Energy Market Operator (AEMO), Victoria has a much lower installed capacity of energy storage than South Australia, New South Wales or Queensland, the other three states with highest energy demand in Australia’s National Electricity Market (NEM).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Victoria has just over 55MW / 80MWh of energy storage in service so far, although there are 320MW / 484MWh of committed projects in the state waiting to be built. Notable projects include the ‘Victorian Big Battery,’ a 300MW BESS under development by French renewables company Neoen and earlier this month infrastructure service provider Lumea opened up a process to tender for another 300MW grid-connected battery project near Melbourne. The state is targeting reaching 40% renewable energy by 2025 and Victoria’s government has said that investment in energy storage will be important in achieving these goals.

Maoneng, which currently operates a 300MW portfolio of large-scale solar and wind, said that the Mornington Peninsula project is part of a 1,800MW battery storage pipeline that it has in various stages of development. It is targeting a late 2022 completion date for its Mornington Peninsula project. In late June the developer submitted plans for a 225MW / 450MWh BESS project in Gould Creek, South Australia.

“As Australia’s electricity grid makes increasing use of renewable generation, we see a bright future for BESS projects,” Maoneng co-founder and CEO Morris Zhou said.

“They provide numerous benefits by operating on a commercial basis to deliver long-term sustainable outcomes that support all stakeholders – from local businesses and communities to the state government, regulators and investors.”

While research published in December by market consulting group Cornwall Insight Australia found that there were over 7GW of battery storage project either proposed or in the planning process in the country, another analysis group, Wood Mackenzie Power & Renewables noted this April that there is a bottleneck of projects, with only 4% of proposed projects having started construction from a pipeline of BESS that companies had hoped to build within two years.

This week, Energy-Storage.news reported that the Australian Energy Market Commission (AEMC) has unveiled new market design rules which it hopes will lower regulatory barriers to participation in the NEM and increase the revenues available from ancillary services markets to energy storage assets.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 7, 2026
Pakistan’s National Electric Power Regulatory Authority (NEPRA) has approved plans to require bidders in a renewable energy auction to include energy storage.
September 7, 2026
Blueleaf Energy and Universal Peak have closed financing for a 100MW/400MWh battery storage project, which was one of four winning bids in a Malaysian government tender.
September 7, 2026
EDF Power Solutions Australia has referred the Wala Wala Pumped Hydro Energy Storage project, a 300-400MW facility in NSW.
September 7, 2026
Copper theft has become a recurring security issue at Australian battery storage sites, with one regulator reporting multiple incidents.
September 7, 2026
OptiGrid has been selected by Vena Energy to provide trading optimisation services for the 408MW Bellambi Heights BESS in Australia.