Australian renewables developer Maoneng reveals details of proposed 240MW / 480MWh battery project

LinkedIn
Twitter
Reddit
Facebook
Email
Rendering of how the 480MWh Mornington BESS project would look. Image: Maoneng.

Renewable energy company Maoneng has made public its plans for a 240MWp / 480MWh battery energy storage system (BESS) which it has proposed to build in Victoria, Australia.

The standalone BESS would be built in Victoria’s Mornington Peninsula, an area subject to fluctuations in demand for power due largely to seasonal tourism. The company said this morning in a press release emailed to Energy-Storage.news that details of the project, which would also aid local electric system reliability and aid the integration of renewable energy on the network, have gone on public exhibition.

A competitive tender process is underway to find a contractor to work on the project, which will be connected to an existing substation and could create 150 jobs during its 12-month construction phase.

According to figures from the Australian Energy Market Operator (AEMO), Victoria has a much lower installed capacity of energy storage than South Australia, New South Wales or Queensland, the other three states with highest energy demand in Australia’s National Electricity Market (NEM).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Victoria has just over 55MW / 80MWh of energy storage in service so far, although there are 320MW / 484MWh of committed projects in the state waiting to be built. Notable projects include the ‘Victorian Big Battery,’ a 300MW BESS under development by French renewables company Neoen and earlier this month infrastructure service provider Lumea opened up a process to tender for another 300MW grid-connected battery project near Melbourne. The state is targeting reaching 40% renewable energy by 2025 and Victoria’s government has said that investment in energy storage will be important in achieving these goals.

Maoneng, which currently operates a 300MW portfolio of large-scale solar and wind, said that the Mornington Peninsula project is part of a 1,800MW battery storage pipeline that it has in various stages of development. It is targeting a late 2022 completion date for its Mornington Peninsula project. In late June the developer submitted plans for a 225MW / 450MWh BESS project in Gould Creek, South Australia.

“As Australia’s electricity grid makes increasing use of renewable generation, we see a bright future for BESS projects,” Maoneng co-founder and CEO Morris Zhou said.

“They provide numerous benefits by operating on a commercial basis to deliver long-term sustainable outcomes that support all stakeholders – from local businesses and communities to the state government, regulators and investors.”

While research published in December by market consulting group Cornwall Insight Australia found that there were over 7GW of battery storage project either proposed or in the planning process in the country, another analysis group, Wood Mackenzie Power & Renewables noted this April that there is a bottleneck of projects, with only 4% of proposed projects having started construction from a pipeline of BESS that companies had hoped to build within two years.

This week, Energy-Storage.news reported that the Australian Energy Market Commission (AEMC) has unveiled new market design rules which it hopes will lower regulatory barriers to participation in the NEM and increase the revenues available from ancillary services markets to energy storage assets.

Read Next

July 27, 2026
Two Australian solar-plus-storage projects advance: Ark Energy secures AU$1.3 billion for 2.2GWh Richmond Valley project; Quinbrook submits 250MWp Queensland site.
July 23, 2026
Spain has awarded €165 million to seven pumped hydro storage projects totalling around 2.1GW/21GWh, while Portugal has set a target of 1.4GW of new pumped hydro capacity by 2040.
July 23, 2026
The Clean Energy Investor Group (CEIG) has published a report calling on the Australian government to prioritise consistent and timely implementation of the reformed Environment Protection and Biodiversity Conservation (EPBC) Act.
Sponsored
July 22, 2026
We caught up with Michael Koller, Solutions Director for Europe and the UK with Envision Energy, at this year’s Smarter E Europe trade show in Munich. 
July 22, 2026
With the Energy Storage Awards 2026 entry deadline less than two months away, we speak to four judges to hear what they are looking for from successful entrants.