APA Group has started construction on its 72MW solar PV plant and 52MW/104MWh battery energy storage system (BESS) at Mount Isa in north-west Queensland, Australia.
APA, an ASX-listed company that owns gas pipelines and power generation assets across Australia, marked the start of works on site alongside the Kalkadoon Traditional Owners, customer Evolution Mining and delivery partner UGL, the company announced on LinkedIn.
The Sybella Creek project sits on land owned by the Kalkadoon Traditional Owners and will supply the North West Power System, an isolated grid serving the region’s mines that has no connection to the National Electricity Market (NEM). APA expects it to deliver power from mid-2028.
The project is underpinned by APA’s long-term energy supply agreement with Evolution Mining’s Ernest Henry Operations, with the 2-hour BESS and solar PV plant firmed by APA’s existing gas-fired Diamantina Power Station.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
“Delivering major energy infrastructure in remote regions relies on strong, respectful partnerships,” APA said.
The company took a final investment decision in August, when APA committed AU$259 million (US$174 million) to Sybella Creek under a supply agreement with Ernest Henry Mining running until mid-2046, as reported by Energy-Storage.news.
UGL, the engineering contractor owned by CIMIC Group, was appointed in September to provide engineering, procurement and construction (EPC) services for the project, which PV Tech reported would be its 16th solar and 12th BESS project.
UGL has worked with APA before, including on the Port Hedland project in Western Australia, which pairs 45MW of solar PV with a 35MW/36.7MWh BESS serving BHP’s iron ore operations. UGL designed, tested and commissioned that BESS for Alinta, which APA acquired in 2023.
The North West Minerals Province has long relied on isolated diesel and gas generation because it has no NEM connection.
That link was meant to come through CopperString, a transmission line from Townsville to Mount Isa, but cost estimates rose from AU$1.8 billion to more than AU$13.6 billion under the previous state government.
The Crisafulli government has since split the project in two. Queensland allocated AU$3.2 billion to CopperString in its 2026-27 state budget, covering the Eastern Link from Hughenden to Townsville, targeted for 2032, and preparatory work on the Western Link to Mount Isa.
The Western Link still has no confirmed construction commitment. In the meantime, the state has opened the AU$200 million North West Energy Fund, managed by Queensland Investment Corporation (QIC), to back local generation and storage in the region.
QIC Infrastructure partner Arash Shojaie told ESN Premium in an interview that proposals need to stand on their own commercially, regardless of whether the Western Link proceeds. Sybella Creek is not funded through the North West Energy Fund.
Other storage concepts have emerged in the area. Mount Isa City Council has said the region could host more than 26GW of co-located solar and wind generation, and has partnered with Glencore and Green Gravity, a gravity-based storage startup.
The three organisations began studies in 2024 on a 2GWh gravitational energy storage project at Glencore’s Mount Isa copper mine, which would use heavy weights and existing mine infrastructure to store energy.
Never miss an Australian energy storage story. Sign up for our Australia newsletter and get the latest project announcements, policy updates and market analysis delivered directly to you.