Equinor’s East Point Energy begins operations at 200MWh Texas BESS

LinkedIn
Twitter
Reddit
Facebook
Email

East Point Energy, owned by Norwegian state-owned energy company Equinor has completed construction and started operations at the 100MW/200MWh Citrus Flatts energy storage project in Harlingen, Texas, US.

Announced 3 September, the Citrus Flatts battery energy storage system (BESS) is East Point’s second operational project, following the start-up of the 10MW/20MWh Sunset Ridge facility last year.

East Point Energy was acquired by Equinor in 2022. In 2024, Equinor gave the green light to East Point to build two BESS projects in Texas.

Those two projects were Sunset Ridge in Frio County and Citrus Flatts in Cameron County, on the border with Mexico.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

At the time, East Point stated that both projects would operate on a fully merchant basis with Equinor’s trading arm, Danske Commodities, providing optimisation services. Real base project returns were expected to be at the higher end of its guided range for renewables of 4-8%.

Equinor has put five BESS facilities into commercial operation over the past four years. The company stated that the projects mark East Point’s “progression from developer to independent power producer (IPP), in line with Equinor’s strategy to capture value across the value chain.”

Outside of Texas, construction has begun on Equinor’s BESS portfolio in Virginia’s PJM market. The portfolio is comprised of four projects totalling 80MW/160MWh and is on track to reach commercial operation in early 2027.

In 2025, East Point had to withdraw plans for a 116MW BESS in New York State after officials from the Town of Carmel placed an indefinite ban on the development of new utility-scale BES facilities.

A representative from East Point told Energy-Storage.news at the time that the project had been “removed from consideration for local approvals” in response to the BESS moratorium.

Texas remains an active market for BESS, despite a growing fleet of assets in competition for revenue opportunities. Last month, Denmark-headquartered multinational energy company Ørsted put its 250MW/500MWh Old 300 BESS project in Needville, Texas into operation. It is collocated with the 430MW solar PV project Old 300 Solar.

Battery Asset Management Summit USA 2026 will be held 15-16 September in Garden Grove, California, hosted by Energy-Storage.news publisher Solar Media (part of the Informa Group). The agenda emphasises addressing the roles of AI, cybersecurity, and second-life applications, broken down into two tracks: Technical Asset Management and Commercial Asset Management. This year, the conference is also co-located with Solar & Storage Finance Summit USA. Visit the official site for more details.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 15, 2026
Energy storage owner-operator Nightpeak Energy has reached financial close and commercial operation on its 150MW/300MWh Bocanova 2 battery storage project in Brazoria County, Southeast Texas.
October 15, 2026
From the Midwest to New York, local and state governments are introducing new zoning rules and restrictions on BESS and data centre projects.
October 15, 2026
ASL has set a target of 1,500MW of new firming infrastructure in NSW by the end of May 2033 and opened a consultation on the tender.
October 14, 2026
The Illinois Power Agency (IPA) is seeking stakeholder feedback on its summer procurement of 600MW of energy storage projects in the US state, after falling short by 438MW.
October 14, 2026
Alberto Valenzuela discusses ahead of Energy Storage Summit Latin America about Mexico’s growing interest in renewables and energy storage, and the factors driving this growth.