Ørsted puts 500MWh Old 300 Texas BESS into operation

LinkedIn
Twitter
Reddit
Facebook
Email

Denmark-headquartered multinational energy company Ørsted has put its 250MW/500MWh Old 300 energy storage project in Needville, Texas, US into operation.

Announced 5 August, the Old 300 battery energy storage system (BESS) is now fully integrated into the Electric Reliability Council of Texas (ERCOT) grid.

Old 300 is collocated with the 430MW solar PV project Old 300 Solar. Ørsted stated that Old 300 Storage is operated independently from Old 300 Solar and “will help improve grid stability by providing power when it is needed most.”

Old 300 Solar has been in operation since 2024. In 2021, Ørsted entered into a power purchase agreement (PPA) with Microsoft for the Old 300 Solar project.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Ørsted claimed that combined, the solar and storage projects will provide approximately US$110 million in property tax revenue that will support local infrastructure, schools, and emergency services. 

Notably, Ørsted procured the BESS solution for Old 300 storage from Tesla, highlighting that the Megapacks deployed at the project were manufactured in Lathrop, California, at Tesla’s Megafactory. Tesla’s Lathrop Megapack factory has an annual production capacity of approximately 40GWh. The company recently reported that it deployed 13.5GWh of energy storage in Q2 2026, its second-highest quarterly figure to date.

Ørsted and Tesla also collaborated with the Needville Fire Department to provide education on the latest BESS technology and safety response protocols.

Originally founded as a national oil and gas exploration company, Ørsted has become one of the world’s largest offshore wind developers, divesting its oil and gas assets in 2017. The Danish government remains the largest shareholder in the NASDAQ-listed company. Ørsted deployed its first standalone BESS project—a 20MW system in the UK—in 2019, followed by a 40MW system in 2021.

In May, Ørsted purchased the 150MW Salzburg BESS project in Michigan from developer ESA Solar Energy. The companies noted that the project’s location makes it well-suited to fulfill Michigan utilities’ offtake needs. 

Texas remains an active market for BESS, with multiple companies advancing BESS projects in June, including Canadian Solar subsidiary e-Storage, developer-operator Spearmint Energy, and developer OCI Energy.

Battery Asset Management Summit USA 2026 will be held 15-16 September in Garden Grove, California, hosted by Energy-Storage.news publisher Solar Media (part of the Informa Group). The agenda emphasises addressing the roles of AI, cybersecurity, and second-life applications, broken down into two tracks: Technical Asset Management and Commercial Asset Management. This year, the conference is also co-located with Solar & Storage Finance Summit USA. Visit the official site for more details.

25 August 2026
Sydney, Australia
Building on our successful global portfolio of energy storage network events including our successful Energy Storage Summit Australia, combined with the exponential buildout of large-scale energy storage, we are delighted to return for the inaugural Battery Asset Management Summit Australia in Sydney (25-26 August 2026). The Battery Asset Management Summit has been received worldwide with huge optimism and has quickly established itself as leading event series for connecting asset owners with optimisers, software providers, and many more.
8 September 2026
Barcelona, Spain
Battery & Energy Storage Tech Europe (BESTE) is Europe’s industrial scaling platform for stationary and industrial battery applications — not EVs. Taking place 8–9 September 2026 at Fira de Barcelona, BESTE brings together utilities, IPPs, energy-intensive industries, data centres, ports, rail, maritime, defence and aerospace OEMs — all deploying or integrating battery storage at scale. Over 100 companies already confirmed — including EDP Renewables, Acciona, Endesa, Naturgy, Neoen, Galp, Basquevolt and Veolia — alongside 40+ expert speakers and international institutional support from BEPA, BVES, LDES and Volta Foundation. Where Europe’s battery & ES ecosystem turns projects into reality.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.
13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

August 6, 2026
Australian Vanadium Limited has signed an MoU with Alcoa to evaluate the deployment of vanadium flow battery technology in Western Australia.
August 5, 2026
Residential energy storage startup Base Power has announced a US$1 billion Series D financing at a US$13 billion post-money valuation, and the launch of its new home battery in production in Austin, Texas, US.
August 5, 2026
Flow battery company Invinity Energy Systems has sold 43MWh of battery systems to utility Dairyland Power Cooperative for deployment across long duration energy storage (LDES) projects in the US Midwest.
August 5, 2026
AMPYR Australia has received a 5.3.4 letter from AEMO for the 270MW Northern Battery near Port Augusta in South Australia.
Premium
August 4, 2026
Energy-Storage.news Premium speaks with Mike Nagus, CEO of LiNova Energy, about the company’s recently launched “metal-free polymer cathode” battery.