Swiss energy company Alpiq has applied for planning approval for a 300MW/1,200MWh battery energy storage system (BESS) in Niedergösgen, in the canton of Solothurn, Switzerland.
The Lausanne-headquartered company said on Thursday (26 November) that it has submitted its application to the Federal Inspectorate for Heavy Current Installations (ESTI), the authority responsible for approving the project, starting the approval procedure.
With an output of 300MW and more than 1.2GWh of storage capacity, giving a 4-hour duration, the BESS will be “among the most powerful battery storage systems in Switzerland”, Alpiq said.
The project is planned on Alpiq-owned land in the Grossacker area of Niedergösgen, between the company’s Gösgen hydropower plant and the Old Aare river, close to existing energy infrastructure and what Alpiq called “a major grid connection point”.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
In June, an agreement in principle with Swiss transmission system operator (TSO) Swissgrid secured 300MW of connection capacity to the national transmission grid, which Alpiq described as the project’s first major milestone.
The plans provide for 72 groups of four battery containers each, 288 containers in total, along with equipment for power conversion and grid connection.
Construction and design will be coordinated with a neighbouring project for a new fish pass. The start of the approval procedure will be followed by a public consultation, and Alpiq plans to present the project to Niedergösgen residents at an information event in mid-January 2027.
Construction is scheduled to begin in 2027, subject to the necessary approvals, with commissioning planned for 2029.
Alpiq first unveiled the Niedergösgen plans in July, shortly after agreeing to acquire UK developer Harmony Energy, when no construction or commissioning dates had been given.
At the time, Amédée Murisier, head of the assets business unit and member of Alpiq’s executive board, said the site sat “at a key node in the Swiss transmission grid”.
If built to plan, the project would be about five times the output of Switzerland’s largest operational BESS facility. Earlier this year, Axpo and energieUri commissioned two Fluence-supplied systems totalling 58.4MW at Gurtnellen in the canton of Uri, with Axpo’s system sized at 50MW and energieUri’s at 8.4MW.
Larger Swiss projects are also in development using other technologies. Swiss developer FlexBase has selected Invinity Energy Systems to design a 1.5GW/2.1GWh vanadium redox flow battery (VRFB) system for a data centre in Laufenburg (Premium access), with Invinity president Matt Harper citing fire safety as the main reason for choosing flow technology.
Alpiq builds out European BESS portfolio
Alpiq said the Niedergösgen project is part of its growth strategy for flexible assets, alongside expanding battery storage in its core European markets and investing in pumped hydro energy storage (PHES).
The company holds a 39% stake in the 900MW/20,000MWh Nant de Drance PHES plant in Switzerland.
The company has built its BESS portfolio largely through acquisitions. It agreed in July to buy a 90% stake in Harmony Energy, whose CEO later described life under its new owner as “business as usual, just accelerated”.
In France, Alpiq bought the 100MW/200MWh Cheviré BESS in the port of Nantes Saint-Nazaire from Harmony Energy, which put it into commercial operation at the end of 2025. That deal followed Alpiq’s November 2024 purchase of an identically sized project in Oise, north of Paris, which was set to come online in August 2026.
More recently, Alpiq acquired the 103.5MW/238MWh Bollingstedt BESS in Schleswig-Holstein, Germany, from owner-operator Eco Stor. Bollingstedt was Germany’s largest operational BESS when it came online in July 2025.
The acquisition made Bollingstedt Alpiq’s third operational BESS, after Cheviré and its fully owned 30MW/36MWh Valkeakoski project in Finland, inaugurated in October 2025. A further 250MW was under construction or close to commissioning at the time.
In June, Alpiq said its secured BESS pipeline across several European markets exceeded 1GW, and the company has said it is targeting a multi-GW operating portfolio by 2030.