1.8GWh Germany BESS moves to construction; 15GWh+ progressed since grid fees decision

LinkedIn
Twitter
Reddit
Facebook
Email

The shareholders of the 900MW Waltrop BESS project in Germany have approved key infrastructure works for the project, with full construction scheduled for the next few months.

Investor Luxcara, power firm BKW and utility grouping vehicle Trianel announced the progress on the 900MW/1,800MWh Waltrop battery energy storage system (BESS) in Waltrop, North Rhine-Westphalia, today (20 July).

Preparatory construction has been underway for ‘several months’, associated substation and key infrastructure works were approved last week while ‘key equipment packages’ have been ordered, they said. Full construction is expected in Autumn 2026, with commissioning scheduled for 2028.

In terms of technical configuration, the project is three separate 300MW units connected to individual transformers. Financially and operationally, it is split into three projects being financed, owned and operated by each of the three shareholders:

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

  • Luxcara: 520MW
  • BKW: 300MW
  • Trianel via its T-BESS 1 arm: 80MW

The companies said that the clarification by regulator BnetzA in May confirming the 4 August 2029 grid fee exemption for large-scale energy storage was a ‘key factor for the project’s economic viability’.

That clarification by BnetzA has been followed by numerous large-scale BESS projects progressing in Germany to final investment decision (FID), offtake and supply deals, or construction.

Last week we published a roundup of BESS projects and portfolios securing financing, offtakers or suppliers, totalling around 2GWh, and published a similar piece at the end of June, covering projects totalling around 2.5GWh combined.

Two weeks ago, BW ESS announced early construction work on a project which may eventually reach 1GW/5.7GWh. We then caught up with BW ESS’ executive director, Roberto Jimenez, who said the grid fee decision was key behind its project progressing, mirroring what Waltrop’s shareholders said. See the full interview about the project with Jimenez here (ESN Premium subscription required).

The period since the decision has also seen Eco Stor secure both finance and offtake for a c.700MWh project, both in June.

Flower secured offtake for two projects totalling 657MWh with utility Engie, in the same month, while Green Flexibility acquired a 2GWh development portfolio.

All-in-all, these projects represent over 15GWh of large-scale BESS capacity progressed since the grid fee announcement.

15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.
2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

August 7, 2026
The German regulator BNetzA’s latest draft decision on grid fees from 4 August 2029 onwards still leaves uncertainty for energy storage project business cases.
August 7, 2026
The Spanish Ministry of Ecological Transition (MITECO) has awarded €360 million (US$415 million) to 1.14GW of solar PV co-located with battery energy storage system (BESS) projects.
August 6, 2026
IPP Zelestra has agreed a long-term toll for a 99MW/297MWh BESS project in Germany with the trading arm of UK-based power group Centrica.
Premium
August 5, 2026
Elestor claims its hydrogen-iron flow battery delivers 75%+ round-trip efficiency, a 20-25 year lifespan, and 15€/kWh capex for long-duration storage. 
August 5, 2026
July was a busy month for large-scale battery storage activity in the UK, with Engie commissioning a system, Masdar and Fidra hitting financial close on projects, Eku Energy buying one, project consents for Aura Power and Starlight Energy, and more.