1.8GWh Germany BESS moves to construction; 15GWh+ progressed since grid fees decision

LinkedIn
Twitter
Reddit
Facebook
Email

The shareholders of the 900MW Waltrop BESS project in Germany have approved key infrastructure works for the project, with full construction scheduled for the next few months.

Investor Luxcara, power firm BKW and utility grouping vehicle Trianel announced the progress on the 900MW/1,800MWh Waltrop battery energy storage system (BESS) in Waltrop, North Rhine-Westphalia, today (20 July).

Preparatory construction has been underway for ‘several months’, associated substation and key infrastructure works were approved last week while ‘key equipment packages’ have been ordered, they said. Full construction is expected in Autumn 2026, with commissioning scheduled for 2028.

In terms of technical configuration, the project is three separate 300MW units connected to individual transformers. Financially and operationally, it is split into three projects being financed, owned and operated by each of the three shareholders:

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

  • Luxcara: 520MW
  • BKW: 300MW
  • Trianel via its T-BESS 1 arm: 80MW

The companies said that the clarification by regulator BnetzA in May confirming the 4 August 2029 grid fee exemption for large-scale energy storage was a ‘key factor for the project’s economic viability’.

That clarification by BnetzA has been followed by numerous large-scale BESS projects progressing in Germany to final investment decision (FID), offtake and supply deals, or construction.

Last week we published a roundup of BESS projects and portfolios securing financing, offtakers or suppliers, totalling around 2GWh, and published a similar piece at the end of June, covering projects totalling around 2.5GWh combined.

Two weeks ago, BW ESS announced early construction work on a project which may eventually reach 1GW/5.7GWh. We then caught up with BW ESS’ executive director, Roberto Jimenez, who said the grid fee decision was key behind its project progressing, mirroring what Waltrop’s shareholders said. See the full interview about the project with Jimenez here (ESN Premium subscription required).

The period since the decision has also seen Eco Stor secure both finance and offtake for a c.700MWh project, both in June.

Flower secured offtake for two projects totalling 657MWh with utility Engie, in the same month, while Green Flexibility acquired a 2GWh development portfolio.

All-in-all, these projects represent over 15GWh of large-scale BESS capacity progressed since the grid fee announcement.

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

September 18, 2026
A roundup of some of our key takeaways from the Energy Storage Summit Germany this week, including around FCAs, inertia, the capacity market (CM), EU restrictions on China, and the future of one very notable system integrator.
September 16, 2026
LFP is the de facto choice for the German BESS market today with sodium-ion still far from bankable, but that doesn’t mean choosing a supplier is necessarily straightforward. 
September 16, 2026
Zelestra and steelmaker Salzgitter Flachstahl have signed a PPA for a new solar-plus-storage portfolio in Germany.
September 16, 2026
Palisade Investment Partners has acquired 100% interests in two development-stage renewable energy projects through Intera Renewables.
September 15, 2026
Flexible Connection Agreements (FCAs) must not be used simply to exclude BESS from connecting to the grid, but the industry will have to make do with them and all their imperfections for the foreseeable.