Edify Energy and Wirsol Energy have connected the 60MW Gannawarra Solar Farm in northwest Victoria to the grid, with a storage retrofit expected before the summer.

The solar farm is connected on site to Powercor’s 66kV distribution line between Swan Hill and Kerang, providing access to Victoria’s power grid. The commissioning process has commenced and once in full production it will provide power to around 18,100 Victorian households.

The solar farm, which is spread over 132 hectares, will be integrated with the Gannawarra Energy Storage System – a 25MW / 50MWh Tesla Powerpack battery – developed by Edify Energy and owned jointly by Wirsol Energy and Edify Energy. The project will therefore demonstrate how existing PV projects can be successfully retrofitted with battery storage.

This element of the project is expected to be completed before the summer this year, at which time the Gannawarra Energy Storage System and the Gannawarra Solar Farm will be amongst the largest integrated solar and storage facilities in the world. This project also features a first-of-its-kind long-term commercial services agreement with the utility EnergyAustralia, who will operate the battery in conjunction with its offtake from the Gannawarra Solar Farm.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Mark Hogan, managing director of Wirsol Energy, said: “The Gannawarra solar farm is in every respect a world leading project and is testament to the future role of solar in enhancing energy supply across Australia.”

Read Next

November 20, 2025
Pacific Green’s Portland Energy Park, Victoria’s largest BESS at 1GW/2.5GWh, has secured federal approval via Australia’s EPBC Act.
November 20, 2025
Battery energy storage systems in Australia’s NEM are facing new operational and revenue challenges due to minimum system load events.
November 19, 2025
Swedish renewable energy developer OX2 has formally taken ownership of the 1.2GW Dinner Hill Wind Farm and the co-located 400MWh Harvest Battery Energy Storage System (BESS) in Western Australia.
November 18, 2025
The 2GWh Kidston Pumped Hydro Project has been registered in the Australian Energy Market Operator’s (AEMO) Market Management System (MMS).
November 17, 2025
Australia’s DCCEEW has announced that the Capacity Investment Scheme Tender 8 will launch later this month seeking 16GWh of energy storage.