Wirsol and Edify connect 60MW solar farm in Victoria, storage retrofit imminent

April 17, 2018
LinkedIn
Twitter
Reddit
Facebook
Email

Edify Energy and Wirsol Energy have connected the 60MW Gannawarra Solar Farm in northwest Victoria to the grid, with a storage retrofit expected before the summer.

The solar farm is connected on site to Powercor’s 66kV distribution line between Swan Hill and Kerang, providing access to Victoria’s power grid. The commissioning process has commenced and once in full production it will provide power to around 18,100 Victorian households.

The solar farm, which is spread over 132 hectares, will be integrated with the Gannawarra Energy Storage System – a 25MW / 50MWh Tesla Powerpack battery – developed by Edify Energy and owned jointly by Wirsol Energy and Edify Energy. The project will therefore demonstrate how existing PV projects can be successfully retrofitted with battery storage.

This element of the project is expected to be completed before the summer this year, at which time the Gannawarra Energy Storage System and the Gannawarra Solar Farm will be amongst the largest integrated solar and storage facilities in the world. This project also features a first-of-its-kind long-term commercial services agreement with the utility EnergyAustralia, who will operate the battery in conjunction with its offtake from the Gannawarra Solar Farm.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Mark Hogan, managing director of Wirsol Energy, said: “The Gannawarra solar farm is in every respect a world leading project and is testament to the future role of solar in enhancing energy supply across Australia.”

Read Next

March 20, 2026
A collaborative team of Australian scientists from CSIRO, the University of Melbourne and the Royal Melbourne Institute of Technology (RMIT) has successfully developed and tested the world’s first proof-of-concept quantum battery system.
March 19, 2026
“When we started back in two years ago, there was a lack of understanding in the market about how the grid-forming inverters operate,” said Ghasem Jahedi, principal grid engineer at AGL.
March 19, 2026
In this US news roundup, updates on solar-plus-storage projects from Google and DTE Energy, Sunraycer, Invenergy and SRP, Idemitsu Renewables, and Clēnera.
March 19, 2026
Australia’s New South Wales now requires 56GWh of storage by 2030, amounting to 40% more than projected just six months ago.
Premium
March 18, 2026
A total of 6.9GW/17.1GWh of grid-scale BESS came online last month, as per the most recent figures from Benchmark Mineral Intelligence.