Return secures financial close, Vattenfall toll for 800MWh Dutch battery

LinkedIn
Twitter
Reddit
Facebook
Email

BESS owner-operator Return has signed a long-term toll with power firm Vattenfall for its 200MW/800MWh Sirius BESS project in the Netherlands, concurrent with financial close. 

The long-term fixed-price toll with Vattenfall helped the project secure project financing under a €400 million (US$463 million) package from banks NG, NatWest, Deutsche Bank, ABN AMRO and Rabobank.

The 4-hour Sirius battery energy storage system (BESS) project in Winschoten, Groningen, will require €180 million in investment, some of which will come from the financing and some from Return. 

Sirius will connect to transmission system operator TenneT’s grid in Meeden under a time-dependent transport rights (TDTR) agreement, similar to a flexible connection agreement (FCA) in Germany. It imposes some constraints on the BESS’ operation, but enables it to connect within existing grid constraints while supporting the wider system, Return said. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Under the agreement, the BESS adjusts when it charges and discharges based on how much capacity is available on the grid at that moment. 

Congestion is a significant challenge on the Dutch grid. So much so that some battery storage projects are being brought online with agreements with TenneT specifically to mitigate congestion

The Sirius project should reach commercial operations in Q4 2027. Return said it is one of the largest fixed-priced tolls in the Netherlands to-date. 

It is the second toll signed between Return and Vattenfall. In April 2025, the pair partnered on the 100MW/200MWh Antares project in Waddinxveen

Sweden-headquartered Vattenfall was in the news last week when a 55MW offtake deal it entered into via the aggregating BESS tolling platform of Terralayr in Germany became fully operational. Vattenfall is also developing its own projects, but has mainly announced offtake roles.  

Return is based in the Netherlands and was an early mover there with its platform SemperPower, which commissioned what were at the time the two largest BESS projects in the country in 2022/23. It also owns Lion Storage, which last year reached financial close on a 350MW/1,400MWh project in the Netherlands. Both platforms have now been folded into SemperPower. Since then Return has also expanded into Germany.

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

September 18, 2026
A roundup of some of our key takeaways from the Energy Storage Summit Germany this week, including around FCAs, inertia, the capacity market (CM), EU restrictions on China, and the future of one very notable system integrator.
September 15, 2026
Flexible Connection Agreements (FCAs) must not be used simply to exclude BESS from connecting to the grid, but the industry will have to make do with them and all their imperfections for the foreseeable.
September 15, 2026
BESS project owners, lenders and optimisers kicked off the Energy Storage Summit Germany 2026 today in Berlin with a discussion on developing a bankable project.
Premium
September 15, 2026
A regulatory change is opening Germany’s energy markets to 23GWh of home batteries. The co-CEO of VPP platform Flexa discusses what it could mean for the market.
September 14, 2026
We hear from the BESS lead at RWE Renewables Europe & Australia ahead of the Energy Storage Summit Germany 2026, discussing the major trends, challenges and opportunities in the country’s grid-scale storage market.