Vopak takes FID on 800MWh Netherlands ‘controllable congestion mitigator’ BESS

LinkedIn
Twitter
Reddit
Facebook
Email

Tank storage company Vopak has marked its energy into the BESS sector with a final investment decision (FID) for a 200MW/800MWh BESS in the Netherlands, which recently entered into a first-of-its-kind agreement with TSO TenneT.

The company has completed a previously announced acquisition of developer Green Energy Storage (GES) and taken FID on its flagship 200MW/800MWh battery energy storage system (BESS) project in Oosterhout, in the Brabant region of northern Netherlands. Vopak’s investments into GES and the project total €230 million (US$262 million).

The Oosterhout project will be among the largest in the Netherlands when it goes into operations in H1 2028. Utility Greenchoice will be offtaker for 50% of the capacity under an 8-year toll.

Grid-scale BESS in the country are typically split into tranches with a variety of offtakers. The market has picked up in the last few years after having been slower to take off than its neighbours in Belgium and Germany, see all our coverage here.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

A Vopak spokersperson confirmed to Energy-Storage.news that the Oosterhout project is the same BESS project that GES entered into a deal with Dutch TSO TenneT for in April this year, labelled as the first of its kind.

GES and TenneT agreed a flexible connection agreement (FCA) called a time-bound transmission right (TDTR), as well as a capacity control contract (CSC). You can read all the details about that in our coverage of the detail at the time, but ultimately the arrangement aims to help TenneT manage congestion on the Dutch grid, which is a huge challenge.

FCAs are also common in Germany, but are highly varied depending on the local DNO or TSO.

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

July 15, 2026
With technology risk now largely removed from the equation, assessing how a battery storage project will perform across market opportunities is now the main object of financiers’ scrutiny, writes Ryan Alexander of enspired.
July 14, 2026
We caught up with the CCO of Netherlands-headquartered startup Moonwatt at last month’s Smarter E Europe trade show in Munich for a video interview.
July 14, 2026
Owner-operator Giga Storage has secured a €450 million (US$512 million) financing package for its 700MW/2,800MWh Green Turtle BESS project in Belgium.
July 13, 2026
According to a leaked draft of its Electrification Action Plan, the European Union (EU) must deploy 200GW of energy storage by 2030 to meet energy system flexibility needs.
July 9, 2026
AI data centre battery storage announcements on both sides of the Atlantic explore the tapping of grid-balancing revenues and distributed computing.