Indian stock market-listed NTPC is seeking parties to deploy 1,000MWh of battery storage across its mix of thermal generation and renewable energy power plants. Image: NTPC.

NTPC, an independent power producer (IPP) in India with over 65GW of power plants across the country wants to install 1,000MWh of energy storage at its existing generation facilities.

The government-owned company has invited Expressions of Interest (EOI) for the installation of battery energy storage systems (BESS) at multiple power plant sites, with the primary aim of enabling higher shares of renewable energy in NTPC and the country’s energy mix.

NTPC operates gas, coal, hydroelectric and renewable energy assets and noted in an EOI document that it is targeting increasing its generation capacity to 130GW by 2032, including 60GW of renewable energy. Meanwhile India’s Central Electricity Authority (CEA) has produced a recent report which said that about 27GW of grid-scale energy storage systems with four-hour storage duration is required by 2030.

The Ministry of Power has supported BESS deployment by stating that it will waiver Interstate Transmission Charges on energy supplied to and from BESS commissioned by mid-2025, if at least 70% of the energy used to charge batteries comes from renewable sources.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

NTPC recognises multiple application, multi-purpose value of battery storage

NTPC said however that while the role of BESS in directly supporting renewable energy sources’ integration to the grid is likely to become well accepted in the near future, for now, the use of fast-responding batteries for high power applications that support the grid, like frequency response and other ancillary services, is already well documented around the world.

In late May, India’s Central Electricity Regulatory Commission drafted ancillary services market regulations that would allow energy storage and demand response sources to participate, helping to maintain the grid’s frequency within the bounds of the 50Hz it needs to operate at. Digitally-enabled batteries are capable of responding within fractions of a second to grid signals to correct the supply and demand of power that maintains the frequency, much faster than fossil fuel plants can, and without the associated emissions.

Grid-scale battery systems the utility is seeking to deploy will have their applications focused mainly on providing primary and secondary frequency reserves to the grid, as well as enhancing the available and quality of power reserves in the grid. However, NTPC recognised the ability of BESS to perform multiple applications and stated that in addition to ancillary services, systems deployed at its thermal or renewable facilities could also perform peak time shifting — storing surplus energy from low demand periods for injection into the grid at peak times.

They could also be used to reduce time taken to ramp up and ramp down thermal generation plants and reduce the amount of Unscheduled Interchange events, when generators are unable to fulfil their capacity injection commitments to the grid. Using BESS for multiple applications will mean they are able to offer the widest range of benefits possible but also justify the high investment costs, NTPC said.

NTPC is seeking BESS projects under design, build and operate or co-investment partnership business models, and it open to other possible business models. Applicants need to have previous experience of installing grid interactive BESS with 5MW / 5MWh cumulative capacity or more.

NTPC listed 23 thermal power plants, 13 solar PV plants and one wind power plant that it operates across various Indian states. The EOI period opened on 26 June 2021 and applicants have until 10 August 2021 to respond before bids open.

2 February 2027
The Tower Hotel, London, UK
Solar & Storage Finance Europe Summit brings together the developers, investors and lenders financing European solar and storage projects. As grid constraints, curtailment and weaker capture prices put pressure on returns, the summit explores what makes projects bankable, how co-located storage changes the revenue case and where capital providers see investable opportunities. Attendees can compare how their peers structure projects and meet people who could help them move their own projects or investments forward.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 27, 2026
Another edition of our BESS Industry Buzz, rounding up some of the hot takes, analysis and gossip from the past week on our feeds.
November 27, 2026
Alpiq has applied for planning approval for a 300MW/1,200MWh BESS in Niedergösgen, in the canton of Solothurn, Switzerland.
November 27, 2026
Blue Elephant Energy has acquired a 95% stake in a 40MW/160MWh BESS project in the Netherlands from developer TPSolar.
November 26, 2026
NYSE-listed energy infrastructure company Energy Vault has reported its Q3 2026 financial results and the close of non-recourse project financing for its 150MW/300MWh SOSA Energy Centre in Texas, US.
November 26, 2026
The first units of a BESS have arrived at European Energy’s operational Mokoan solar PV plant in northern Victoria, Australia.