Australia prepares to open fast frequency response ancillary services market

LinkedIn
Twitter
Reddit
Facebook
Email
The 30MW / 30MWh Ballarat Battery Energy Storage System, inaugurated in October 2018 and welcomed by Lily D’Ambrosio, Victoria’s Minister for Energy, Environment and Climate Change (centre). Image: State of Victoria Government.

The Australian Energy Market Commission (AEMC) has drafted a new rule to enable the provision of fast frequency response services to help keep the electricity grid stable which one expert said will be “a really important market for batteries”.

As the use of synchronous thermal generation — mainly gas and coal — declines and will continue to decline in the coming years, the need to balance supply and demand on the grid at very short intervals will increase. With fast frequency response, power is delivered to or withdrawn from the grid within two seconds or less, helping to maintain the Australian grid’s operating frequency to within a very narrow boundary of 50Hz as required.

While fossil fuel power plants (and hydroelectric power) provide synchronous inertia to the electric system, the retirement of coal and gas, coupled with the growth of renewable energy means that a further need for frequency regulation services is anticipated. This can be done using inverter-based technologies like wind, solar, demand response and — particularly for services where extremely quick response times are needed — batteries.

Some large-scale batteries deployed in Australia have already been proven capable of delivering frequency response through the Frequency Control Ancillary Services (FCAS) market, as have small-scale distributed batteries aggregated into virtual power plants (VPPs), studies have shown. The 30MW / 30MWh Ballarat Battery Energy Storage System in Victoria made AU$6.07 million (US$4.42 million) in its first year of operation from FCAS, for example, while a VPP in South Australia comprising 1MW of aggregated home batteries made AU$132,047 in one day in December 2019 through responding to five frequency events caused by a storm. These batteries, mostly deployed in the last couple of years, have shown that they can earn revenues for delivering a vital service.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, a market for frequency response with response times under six seconds has not yet been developed until now, Lillian Patterson, director of energy transformation at Australia’s Clean Energy Council, told Energy-Storage.news.

“Today, the Australian Energy Market Commission, the rule-maker in relation to the market framework, has come out with a draft determination to say that they will develop a fast frequency response market,” Patterson said.

“We have a frequency control ancillary services market at the moment, but they don’t do fast frequency response. So they don’t value less-than-six second frequency response. There’s kind of different markets for different timeframes, but it’s from six seconds onwards that they’re valued.”

Patterson said that this developing opportunity is “a really important one for batteries, because batteries would operate really well in it, because they do provide a really fast response and it’s about speed and accuracy. And that’s what batteries do”.

The fast frequency response market would incentivise further development of batteries, because it values a service batteries can provide better than other technologies. Australia’s renewable energy and energy storage industries have been calling for the introduction of such a market for a while, describing it as a “no regrets” solution to a fundamental challenge facing the network, Patterson said. Clean Energy Council represents dozens of industry stakeholder companies in its membership.

After today’s draft rule announcement, the AEMC is taking comments and input until June, before a final rule decision is expected to be issued in July. From there, it could be a process of around three years before the market opportunity is opened. Patterson said that the need for the service “will be absolutely critical” in a few years’ time.

“We should be implementing this type of market as quickly as possible to provide the incentive for new technologies, such as batteries, to come in before it’s actually critical that it’s needed. It’s in a few years’ time that it will be absolutely critical that we have this service and we need to have that framework in place to create the incentive for the technologies to be in place.”

AEMC’s draft rules can be found here.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 21, 2026
The US energy storage industry is targeting 225GW/1TWh of storage deployment by the end of 2032, according to an analysis published by the Energy Storage Coalition (ESC).
September 21, 2026
The Tailem Bend BESS 3 in South Australia and Wooreen BESS in Victoria have both entered the AEMO Market Management System (MMS).
September 21, 2026
Flow Power has broken ground on its 100MW/223MWh Bennetts Creek BESS in Victoria, its first large-scale standalone BESS project.
September 18, 2026
All BESS and demand response projects selected under ASL’s 2023 firming tender for New South Wales, Australia, are now operational.
September 17, 2026
Alinta Energy has received the first shipment of battery units for its 250MW Reeves Plains Battery project in South Australia.