One of the largest battery energy storage system (BESS) projects so far in Belgium has been brought online at the site of a former coal power plant.

The European subsidiary of Japanese engineering consultancy Nippon Koei announced the news today, together with its development partner on the project, Aquila Clean Energy EMEA.

The 25MW/100MWh project is in the town of Ruien, East Flanders, on the site of what was an 800MW coal-fired power station. As with other projects of its type around the world, the BESS plant was able to leverage the thermal power plant site’s existing infrastructure, including the connection point to the Belgian high voltage grid.

This meant the project was able to leapfrog the challenges of connecting to an already congested grid – something that has been a barrier to rapid energy storage, and other new energy resource, deployment in many parts of the world, including the neighbouring Netherlands.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

An exact date for when commissioning took place was not given but a release sent to media including this site noted that the Ruien BESS is already participating in short-term grid-balancing flexibility markets.

As noted by Energy-Storage.news when the project achieved financial close in November 2021, shortly after netting a long-term Capacity Remuneration Mechanism (CRM) contract, it had been originally scheduled to go into operation in Q4 2022. The CRM was newly introduced in 2021 and the contract for Ruien was won in the inaugural September 2021 auction.

At that time of financial close, Nippon Koei Energy Europe said it was working with Belgian renewable energy company Yuso on the project, with the engineering company acting as lead developer. Nippon Koei acquired a 29% stake in Yuso back in 2019.

Yuso originated the project’s planning in 2018, and will serve as the optimiser for its route-to-market activities over a 10-year period using its YusoFlex platform.

Meanwhile Aquila Clean Energy EMEA is the development arm of sustainable infrastructure investor Aquila Capital, partnering with Nippon Koei on financing, procurement, development and the BESS’ operation.

Other parties working on the project included technology provider Wärtsilä and independent energy and communications engineering services company SPIE, while Nippon Koei Energy Europe delivered the project through a fully-wrapped EPC contract. Nippon Koei Energy Europe and Aquila Capital are the shared owners of the project.

It is the same size as another BESS project currently underway in Belgium by Nala Renewables – a joint venture (JV) of commodity trader Trafigura and IFM Investors. That one is being built on the site of a zinc smelting plant in the municipality of Balen, and construction began last spring.

Both are rare early examples of four-hour duration large-scale lithium-ion battery storage projects in Europe. As for Belgium, the country’s largest project to date by megawatts, although equal in energy capacity to Ruien and Balen, is a 50MW/100MWh system brought online near the end of 2022 in the Wallonia region, inaugurated by developer Corsica Sole. Belgium’s largest operational BESS project prior to that was the 10MW/20MWh EStor-Lux project, brought online in April last year.

Read Next

Premium
January 28, 2026
Leading BESS owner-operators across Europe discuss the key trends around the financing and deployment of grid-scale projects, with the segment now the driver of continent-wide deployments according to trade body SolarPower Europe.
January 27, 2026
Germany’s four transmission system operators (TSOs) have begun procuring inertia services to help stabilise the electric grid as shares of renewable energy grow.
January 21, 2026
Sahand Karimi and Henry Swisher of OptiGrid examine the two primary metrics used to evaluate the performance of battery storage trading: normalised revenue and percentage of perfect capture rate.
January 20, 2026
Global infrastructure investor I Squared Capital has launched ANZA Power, a next-generation independent power producer (IPP) in Australia and New Zealand.
January 15, 2026
Torrent Power has contracted Larsen & Toubro to construct a 3GW pumped hydro energy storage (PHES) plant in Maharashtra, India.