ERCOT: EsVolta finances 290MW, Fluence wins project via Linxon EPC partnership

LinkedIn
Twitter
Reddit
Facebook
Email

EsVolta has completed over US$180 million in financing for battery energy storage system (BESS) projects in the ERCOT, Texas market, while system integrator Fluence has won a 200MWh project there via a new partnership with EPC firm Linxon.

EsVolta, a Newport Beach, California-based developer owned by investor Generate Capital, has closed a US$126.1 million project financing facility with MUFG Bank for its 140MW/280MWh City Breeze BESS in Bay City, Texas.

The facility includes a construction loan, a tax equity bridge loan, a letter of credit facility and a term loan, covering both the build and long-term operation of the 2-hour duration project, which will serve the market, where ERCOT is the grid operator.

EsVolta also closed a US$55.1 million tax equity financing with East West Bank covering City Breeze and its Boxcar project in Wylie, Texas, sized at 150MW/300MWh. EsVolta did not give construction or commissioning dates for either project.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Together, City Breeze and Boxcar add 290MW/580MWh of flexible capacity to ERCOT, where rapid load growth makes energy storage essential to grid reliability and to meeting rising electricity demand,” said Randolph Mann, CEO of esVolta.

Fred Zelaya, managing director, project finance at MUFG Bank, said “energy storage is critical infrastructure for a growing grid”, adding that the bank wants to support experienced developers scaling up in markets such as ERCOT.

A day earlier, Charge Power, an owner’s-side BESS services firm with offices in Austin and Toronto, said it will manage two ERCOT projects of exactly those sizes, 150MW/300MWh and 140MW/280MWh, through commissioning to commercial operation date (COD), expected in 2027.

Charge Power did not name the projects or their owner, and while they are likely to be City Breeze and Boxcar, this has not been confirmed.

Charge Power will coordinate EPC contractors, engineers, suppliers, documentation and the ERCOT interconnection checklist on the owner’s behalf. Both projects are also adopting the WARAM platform for project governance, due diligence and compliance records.

“The stretch between construction and commercial operation is where a project either protects its returns or loses them,” said Ravi Pinnelli, founder and president of Charge Power.

EsVolta said it now has over 1.5GWh of projects operational and under construction in Texas, out of roughly 2GWh in total, backed by more than US$1 billion of funding to date, and a pipeline of over 35GWh.

Its existing Texas fleet includes the Anole, Desert Willow and Burksol projects, totalling 490MW/980MWh, which esVolta brought into commercial operation between March and July 2025 with EPC contractors Saber Power and Quanta Infrastructure Solutions Group.

That trio was backed by a preferred equity deal with Captona expected to provide US$243 million, including tax credit transfer proceeds, following an earlier US$185 million pre-NTP credit facility led by Nomura for its US pipeline.

ERCOT clears projects for commercial operation in monthly batches. In one June round, it cleared 650MW of BESS for COD across five projects (Premium access), including Engie’s Five Wells and two Plus Power projects.

Citing Modo Energy, Charge Power said BESS capacity on the ERCOT grid roughly doubled each year from 2020 to 2024, grew another 76% in 2025 and reached 16.5GW/28.8GWh by the end of June 2026.

In a guest feature on leading US BESS markets, Rabobank’s Amit Mathrani noted that ERCOT grew from about 0.5GW to 10GW of BESS between 2020 and 2024, with projects typically taking 18 to 30 months from application to energisation.

Fluence and Linxon pair OEM and EPC roles

Fluence said its collaboration with Linxon, which provides high-voltage engineering, grid connection and project execution, has already contributed to securing a 200MWh BESS project in ERCOT. It did not name the customer, site, power output or delivery timeline.

The agreement is the first under Fluence PACE (Partner Advancement, Collaboration, and Enablement), a new programme through which Fluence will jointly approach customers and coordinate project delivery with selected partners. The two companies are pursuing further projects together.

Linxon will apply its “Mission Ready EPC” approach, which centres on readiness planning, interface management, constructability reviews and risk identification before mobilisation on site.

“We want to redefine the traditional relationship between an OEM and an EPC,” said Nicolas Sanloup, managing director, Americas, at Linxon. “It is about engineering the mission together from the beginning.”

Jeff Monday, SVP and chief growth officer at Fluence, called PACE “a strategic accelerator that allows us to scale faster”, adding that the company is being deliberate about where partner relationships can strengthen its competitive position.

Fluence said PACE is aimed at utilities, independent power producers (IPPs), developers and data centre customers. The launch follows a period of change at the Nasdaq-listed company, which cut its 2026 revenue and EBITDA guidance as US production delays hit.

On 2 November, Fluence named Siemens and AES veterans Axel Meier and Ricardo Roizen as interim CEO and interim CFO, after CEO Julian Nebreda and CFO Ahmed Pasha left with immediate effect.

26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 18, 2026
AGL Energy has received federal environmental clearance for a 500MWh battery energy storage system in Queensland under Australia’s EPBC Act.
November 17, 2026
EnerVenue CEO Henning Rath discussed its first multi-MWh order, its North American push, and the policy uncertainty shaping battery manufacturing in the US.
November 17, 2026
Spain-headquartered power conversion system (PCS) manufacturer Power Electronics is supplying grid-forming inverters and DC/DC converters for Edify Energy’s Smoky Creek and Guthrie’s Gap solar-plus-storage projects in Queensland, Australia.
November 17, 2026
ASX-listed Frontier Energy has started construction on Stage 1 of its Waroona Renewable Energy Project in Western Australia (WA), which pairs solar PV with a battery energy storage system (BESS).
November 16, 2026
US energy storage developer Flatiron Energy has broken ground on its 250MW/1,200MWh Energizar Energy Storage Project in Chelsea, Massachusetts, US.