Refinancing deal for 50MW UK battery ‘proves bankability of storage’ is here

June 27, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
The 50MW Pelham battery energy storage system. Image: Statera.

Energy asset developer and owner Statera Energy has clinched a refinancing deal for its 50MW Pelham utility-scale battery storage plant in England, in a transaction which it says demonstrates both the maturity and “bankability” of the asset class.

The refinancing package has been sealed with high street bank Natwest and is one of the first for a battery storage asset in the UK.

The 49.9MW facility was commissioned in December 2017 and as such has now been operational for six months. It clinched a two-year Firm Frequency Response contract to provide services to National Grid and also has a 15-year Capacity Market contract, commencing in 2020/21.

Tom Vernon, managing director at Statera Energy, said that the refinancing package demonstrates the bankability of battery storage and praised Natwest’s “pragmatic” approach which was “essential in structure financing of this nature”.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

“We believe that battery storage will play a pivotal role in facilitating the UK’s transition to low carbon generation and thanks are due to all parties involved in delivering this landmark project. It has been an immense team effort where we have benefited from the full support and cooperation of UK Power Networks and National Grid,” Vernon added.

Natwest meanwhile said it was “delighted” to play a pivotal role in facilitating this “milestone transaction”.

“Natwest is committed to becoming a more sustainable bank and supporting the UK’s ambition to become a low carbon economy is an important part of this,” the bank’s director Steve Guy added.

Read Next

Premium
October 16, 2025
How you approach fire safety risk management in BESS was a big talking point yesterday at the Battery Asset Management Summit UK & Ireland 2025.
October 16, 2025
Octopus Australia has acquired the Coleambally battery energy storage system (BESS), a 100MW/400MWh standalone project in development located in southern New South Wales.
October 15, 2025
The value of developers and optimisers in the BESS lifecycle, thinking about long-term risk and KPIs for maximising the asset have been key themes at the Battery Asset Management Summit UK & Ireland 2025.
October 15, 2025
Takeaways from the first day of Energy Storage Summit Latin America 2025, including the Chilean and Argentinian markets.
October 13, 2025
Queensland’s Energy Roadmap 2025 suggests that by 2030, up to 4.3GW of short-duration energy storage could be operational.

Most Popular

Email Newsletter