NV Energy and EDF sign PPA for Nevada solar plant with 180 MW / 720MWh battery storage

July 31, 2020
LinkedIn
Twitter
Reddit
Facebook
Email

Independent power producer EDF Renewables North America has signed a 22-year power purchase agreement with utility NV Energy for a 200MWac solar project coupled with a 180MW, four-hour battery storage system (720MWh).

Located around 35 miles northeast Las Vegas, Nevada, the Chuckwalla Solar+Storage project is expected to come online by the end of 2023. For context, the project is slightly smaller than the PG&E-Tesla Moss Landing substation battery project (182.5MW / 730MWh) which has just begun construction in California’s Monterey County, currently one of the biggest lithium-ion battery projects in development in the world – and set to be eclipsed by a 1,000MWh+ facility in the same region under development by Vistra Energy.

Meanwhile in May, authorities gave approval to the US$1 billion Gemini Solar Project in Nevada, a hybrid resources project combining 690MW of solar PV with a 380 MW / 1,400MWh of battery storage, again with NV Energy as the offtaker.

“The battery and solar system work together to provide more energy during the summer evening peak hours when system needs are the greatest,” said Ian Black, vice president, west region development at EDF Renewables North America.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“NV Energy can utilise the battery at their discretion in all months of the year, allowing mitigation of demand spikes.”

Plans for the Chuckwalla plant and two other Nevada solar farms were announced by NV Energy last week. The three solar-plus-storage projects, which form part of the utility’s Integrated Resource Plan (IRP) filing, total 478MW of new solar photovoltaic generation and 338MW of battery storage.

The Chuckwalla collaboration builds on the 2019 agreement between EDF Renewables and NV Energy to develop the Arrow Canyon Solar+Storage project, also located in Nevada.

EDF Renewables’ North American portfolio consists of 16GW of developed projects and 10GW under service contracts.

This story first appeared on PV Tech. Additional reporting for Energy-Storage.news by Andy Colthorpe.

Read Next

April 21, 2026
Danish investment firm Copenhagen Infrastructure Partners (CIP) has begun construction on the 300MW/1,500MWh Patache battery energy storage system (BESS) in northern Chile.
April 20, 2026
In this US news roundup, Eos and Turbine-X, CPower and Vertiv, and Elevate Renewables highlight the ‘bring your own capacity’ model in data centre-focused announcements.
April 20, 2026
HD Renewable Energy and utility Tokyo Gas signed a deal for two large-scale projects in another busy week for Japan’s growing battery storage market.
April 13, 2026
Brazil’s national regulator, ANEEL, postponed an important decision on energy storage, days after approving the country’s first hybrid plant.
April 9, 2026
Maxxen managing director Ruben Valiente speaks with Energy-Storage.news editor Andy Colthorpe at Energy Storage Summit 2026 in London.