Ireland’s system operator sets out conditions for 300MW grid services tenders

By David Pratt
April 3, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
Image: National Grid.

Storage developers eyeing opportunities in Ireland’s DS3 programme will be able to bid for six-year contracts providing frequency response and reserve services in September when transmission system operator EirGrid will launch a new procurement process.

But a number of stipulations have been put in place to cap the volume of applications that could be put forward to limit any expenditure risks identified by the TSO.

The proposed ‘Volume Capped’ procurement process outlined in a consultation published on 29 March sets out which of the DS3 system services will be up included in this year’s auction.

For the full story, visit sister title Clean Energy News.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

February 6, 2026
NSW concludes Australia’s largest LDES tender, awarding six battery projects 12GWh. Industry calls it “game-changer” for grid reliability.
February 6, 2026
The NSW government has declared two pumped hydro projects totalling 22,000MWh of storage capacity as critical infrastructure.
Premium
February 5, 2026
Energy-Storage.news Premium speaks with Noon Energy co-founder and CEO Chris Graves about the company’s approach to long-duration energy storage.
February 5, 2026
A framework for the “development, utilisation and commercialisation of energy storage systems” in the Philippines has been passed by the House of Representatives.
February 4, 2026
IPP Enlight Renewable Energy has reached development milestones for its total 1.21GW solar plus 4GWh energy storage CO Bar Complex in Arizona, US, and is now advancing the project toward operation.