Fire at 20MW UK battery storage plant in Liverpool

By Andy Colthorpe
September 16, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Carnegie Road BESS in Liverpool, UK, as it looked when completed in early 2019. Image: Ørsted.

There has been a fire at the Carnegie Road 20MW battery energy storage system (BESS) project in Liverpool, England, project owner Ørsted has confirmed.

Merseyside Fire & Rescue Service, local first-responders, said that crews were alerted shortly before 1am on 15 September and arrived to find a “large grid battery system container well alight”.

The fire service said that it had used main jets and ground monitors in tackling the fire, asking residents nearby to keep their windows and doors closed due to smoke from the incident.

The blaze went on for several hours, with an update from the service at 7:30am noting that although operations at the site had been scaled down, firefighting was ongoing, with two ground monitor units and a main water jet still in use. A further update at 11:45am said one fire engine was still at the scene, with firefighting still continuing, although by that stage only one hand-held pump was in use.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The Carnegie Road project was Danish power company Ørsted’s first standalone grid-connected battery project, built using storage system equipment supplied by the now-defunct Energy Solutions division of NEC Corporation, housed in three containers. The project’s completion was announced at the beginning of 2019.

Ørsted sent a statement to Energy-Storage.news in response to a request for confirmation of the story and for further details:

“We can confirm there has been a fire at our Carnegie Road battery storage facility in Liverpool. This facility does not have permanent members of staff and no-one was on-site at the time of the fire,” the spokesperson said.

“We would like to thank the firefighters at Merseyside Fire and Rescue for their rapid response and professionalism in getting the fire under control. It is too early to speculate about the cause of the fire but as soon as we can get on-site we will be conducting an urgent review to understand what has happened.”

Merseyside Fire & Rescue Service also said that “an investigation will be carried out”.

Read Next

November 14, 2025
BESS and flexible generation provider Statera Energy has secured £235 million (US$309 million) in debt financing for its 680MW/1,360MWh Carrington BESS project in Manchester, UK.
November 13, 2025
The three-year rolling partnership, whereby CATL will supply HyperStrong with cells and system products, could be updated annually.
November 13, 2025
Ampyr Australia has acquired the 270MW Davenport battery energy storage system (BESS) in South Australia from Green Gold Energy (GGE), renaming the facility the ‘Northern Battery’.
Premium
November 12, 2025
Energy-Storage.news Premium speaks with Joe DeBellis, Global Head of Clean Energy at Firetrace International, about the company’s latest report detailing public support for battery energy storage systems (BESS).
November 12, 2025
Three large-scale BESS with a combined capacity of 720MW have been submitted for federal assessment under Australia’s EPBC Act.