Fire at 20MW UK battery storage plant in Liverpool

By Andy Colthorpe
LinkedIn
Twitter
Reddit
Facebook
Email
Carnegie Road BESS in Liverpool, UK, as it looked when completed in early 2019. Image: Ørsted.

There has been a fire at the Carnegie Road 20MW battery energy storage system (BESS) project in Liverpool, England, project owner Ørsted has confirmed.

Merseyside Fire & Rescue Service, local first-responders, said that crews were alerted shortly before 1am on 15 September and arrived to find a “large grid battery system container well alight”.

The fire service said that it had used main jets and ground monitors in tackling the fire, asking residents nearby to keep their windows and doors closed due to smoke from the incident.

The blaze went on for several hours, with an update from the service at 7:30am noting that although operations at the site had been scaled down, firefighting was ongoing, with two ground monitor units and a main water jet still in use. A further update at 11:45am said one fire engine was still at the scene, with firefighting still continuing, although by that stage only one hand-held pump was in use.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The Carnegie Road project was Danish power company Ørsted’s first standalone grid-connected battery project, built using storage system equipment supplied by the now-defunct Energy Solutions division of NEC Corporation, housed in three containers. The project’s completion was announced at the beginning of 2019.

Ørsted sent a statement to Energy-Storage.news in response to a request for confirmation of the story and for further details:

“We can confirm there has been a fire at our Carnegie Road battery storage facility in Liverpool. This facility does not have permanent members of staff and no-one was on-site at the time of the fire,” the spokesperson said.

“We would like to thank the firefighters at Merseyside Fire and Rescue for their rapid response and professionalism in getting the fire under control. It is too early to speculate about the cause of the fire but as soon as we can get on-site we will be conducting an urgent review to understand what has happened.”

Merseyside Fire & Rescue Service also said that “an investigation will be carried out”.

Read Next

October 21, 2026
Spain-headquartered power electronics manufacturer Ingeteam has supplied power conversion systems (PCS) for around 65MW/130MWh of battery storage projects in Victoria, New South Wales (NSW) and South Australia.
Premium
October 20, 2026
A panel at the Battery Asset Management Summit UK & Ireland 2026 last week discussed BESS capex trends and strategies to manage it.
October 20, 2026
Genesis Energy has officially opened its first grid-scale battery energy storage system (BESS) at Huntly Power Station on New Zealand’s North Island.
October 20, 2026
ENGIE’s Hazelwood battery energy storage system (BESS) expansion in Australia has moved closer to financial close after a state transmission declaration.
October 20, 2026
Australian battery energy storage system (BESS) developer Akaysha Energy has refinanced its project debt into an AU$1.75 billion (US$1.22 billion) portfolio-level facility.