Kyon Energy puts 282MWh Alfeld battery storage project in Germany into operation

LinkedIn
Twitter
Reddit
Facebook
Email

BESS developer Kyon Energy has commissioned and put into operation its 137.5MW/282MWh Alfeld BESS project in Germany, potentially the country’s largest to reach that milestone. 

Kyon announced the commissioning of the battery energy storage system (BESS) project in Lower Saxony on LinkedIn yesterday (27 October). 

The project is in the service area of DNO Avacon Netz, which Kyon thanked along with Engira, another developer and renewables services provider which also worked on the project. 

Kyon secured planning approval for the project in late 2023, when it ambitiously called it the ‘largest BESS project in Europe’, although made no such claim in its post yesterday. Since then Germany has moved up in scale, with several gigawatt-hour projects in construction including three announced this month.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The Alfeld project is part of a portfolio of Kyon projects that Belgium-based investor Scale Fund is financing and owning. Battery analytics firm Twaice is providing its services on the project while renewables developer and services firm BayWa r.e. is doing O&M and technical asset management. 

Shortly after BayWa r.e. won the contract, the firm’s MD data services Simon Slapka spoke to us about the state of play for O&M and asset management in BESS today for an ESN Premium video interview article. 

Kyon Energy was acquired by oil and gas major TotalEnergies in January 2024 and is building a 789MW/1,628MWh portfolio of BESS projects in Germany for its parent company, but the Scale Fund’s investment pre-dated that deal so Kyon has continued to work with it. TotalEnergies then divested 50% of that portfolio to Allianz GI this year. 

The Alfeld news comes as Germany’s grid-scale storage market enters a phase of busy project execution ahead of a 4 August 2029 commissioning cut-off date for projects to be exempt from charge-discharge grid fees. 

Our publisher Solar Media, part of Informa Markets, held the Energy Storage Summit Germany in Berlin last month where grid fees and flexible connection agreements (FCAs) were among the biggest topics. 

Read Next

November 13, 2026
Another edition of our BESS Industry Buzz, this week looking at new details on CATL’s sodium-ion technology, BESS availability, BAAJA trade-offs and the price of speed to power.
November 12, 2026
Stadtwerke Gaggenau, a municipal utility in Germany, has hired a general contractor to build a 4-hour BESS project using the zinc-bromide technology from US firm Eos Energy Enterprises.
November 11, 2026
Envision Energy will supply its Gen 8 BESS platform for ju:niz Energy’s 442MWh Smareg 13 project in Bavaria, Germany.
November 5, 2026
BESS owner-operator Return has secured an €835 million (US$938 million) portfolio financing underwritten by Deutsche Bank and Rabobank to expand its BESS activities in Germany.
November 3, 2026
Battery storage projects have won nearly 40% of the capacity in Belgium’s latest capacity market (CM) auction results, while Germany’s first has all gone to gas, paying nearly eight times more than Belgium in the process.