Genex achieves contractual close for 100MWh Queensland battery project

LinkedIn
Twitter
Reddit
Facebook
Email
Genex solar farm in Kidston, Queensland, close to the site of the 2GWh PHES plant the company has under construction. The 50MW PV facility pictured is being expanded to 270MW to integrate with the pumped hydro. Image: Genex.

Clean energy developer Genex Power has “secured the final piece” of its project finance package for the 50MW/100MWh Bouldercombe Battery Project (BBP) in Queensland, Australia. 

Genex made an announcement to the Australian Securities Exchange (ASX) this morning. Having received firm commitments to a AU$40 million (US$29 million) capital raise to fund the project, it has now achieved contractual close for the standalone battery energy storage system (BESS). 

The announcement comes just two days after Energy-Storage.news reported that Genex had agreed a AU$35 million debt finance facility for BBP from specialist project finance fund manager Infradebt under a 12-year term.

Tesla will supply 40 of its Megapack grid-scale battery storage units to the project and the US tech company’s Autobidder trading and bidding platform will control its market-facing activities. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Genex said the AU$40 million institutional placement, alongside the Infradebt loan, will go towards project construction costs as well as repay an existing debt facility to Australia’s national Clean Energy Finance Corporation and provide further working capital. 

“I am delighted to announce today the final piece for the project financing of the Bouldercombe Battery Project, being the completion of a AU$40 million institutional placement,” Genex Power CEO James Harding said, thanking the company’s existing institutional shareholders and welcoming new ones. 

“In acknowledgement of this support, I am pleased to confirm the launch of a AU$10 million Share Purchase Plan to allow our retail shareholders to participate in the capital raising on similar terms to investors under the institutional placement.”

Bouldercombe, along with Genex’s large-scale pumped hydro energy storage (PHES) plant under construction at Kidston, also in Queensland, “will add significant upside exposure for shareholders when it commences operation,” scheduled for mid-2023, Harding said. 

Read Next

August 11, 2026
Danish investment firm Copenhagen Infrastructure Partners (CIP) has reached financial close of the La Esperanza Solar energy storage-plus-solar PV project in the state of Campeche on Mexico’s Yucatán Peninsula.
August 11, 2026
The Clean Energy Finance Corporation committed a record AU$9.1 billion (US$6 billion) in the financial year to 30 June 2026.
August 10, 2026
Avantus has closed a US$1.05 billion corporate credit facility to support the company’s IPP strategy and accelerate development of its solar and energy storage portfolio.
August 7, 2026
ZEBRE has submitted the 180MW/360MWh Noblevale Battery in Queensland for federal environmental assessment under the EPBC Act.
August 6, 2026
Australian Vanadium Limited has signed an MoU with Alcoa to evaluate the deployment of vanadium flow battery technology in Western Australia.