The Energy Storage Report 2024

Now available to download, covering deployments, technology, policy and finance in the energy storage market

Underground works begin at 250MW Kidston pumped hydro plant in Australia

LinkedIn
Twitter
Reddit
Facebook
Email
The Kidston site. Image: Genex Australia.

“Extensive works” to house two 125MW turbines have begun at Australia’s first new pumped hydro energy storage (PHES) plant in nearly 40 years, developer Genex Power has said. 

Underground works began over December at the 250MW Kidston Stage 2 Pumped Hydro Project, renewable energy development company Genex said in a construction update provided to the Australian Securities Exchange (ASX) yesterday.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The works relate to the project’s 1.5km long, 6 metre x 6 metre Main Access Tunnel (MAT), which will provide access to the powerhouse cavern which will house the turbines, about 250 metres underground. 

It will take about six months to drill and blast the first heading to the cavern, with multiple headings then planned, which will expedite excavation of the powerhouse cavern itself. About 8 metres per day of tunnelling works are expected over the next six months.

The project achieved financial close in May 2021. Its planned capacity will be 2,000MWh and Genex has said it expects construction to be completed by 2024, with engineering, procurement and construction (EPC) duties carried out by a consortium of two companies, John Holland and McDonnell Dowell. 

Located at a former goldmine site in Kidston, Queensland, the project is expected to cost about AU$777 million (US$600 million) in total, including the cost of building transmission infrastructure to carry power to the northeast coast of Australia around 190km away. The plant will also be connected to the National Electricity Market (NEM). 

Financing close was achieved with AU$620 million debt equity pledged by the Commonwealth Government’s Northern Australia Infrastructure Facility, as well as AU$147 million from the state government of Queensland. The latter sum will go towards the transmission upgrade, while the Australian Renewable Energy Agency (ARENA) also approved AU$47 million funding support for the project. 

It will be Australia’s first new PHES facility built since 1984. In July last year, the state government of Queensland committed AU$14 million to refurbishing and modernising the 570MW Wivenhoe Pumped Storage Hydroelectric Power Station, which was the plant opened in 1984. 

In October, Genex signed a supply agreement with Tesla for the developer’s 50MW / 100MWh Bouldercombe Battery Project (BBP) in Queensland. BBP will comprise 40 Tesla Megapack battery energy storage system (BESS) units. It will be Genex’s first standalone battery storage project.

Australia second to China for pumped hydro plans in Asia-Pacific

Two other new significant PHES capacity additions in development in Australia are the Snowy Hydro 2.0 project which will retrofit project which could increase capacity of an existing plant to 2GW and as much as 350GWh and Oven Mountain, a 600MW/7,200MWh new-build PHES. Both are in New South Wales.

In December, the State Grid Corporation of China brought online two generating units at the 3.6GW Fengning Pumped Storage Power Plant in China’s Hebei province. Twelve 300MW reversible pump turbines were commissioned and integrated into the North China Power Grid and the State Grid Corporation said they are expected to be put into operation during this year.

The Fengning PHES system will support greater integration of renewable energy into the grid, as well as supporting the running of the Beijing Winter Olympics this year. 

According to figures issued by research and analysis group IHS Market last year, China leads the Asia-Pacific region for pumped hydro in construction or planning. The country’s energy companies had about 52.3GW of a total 71GW across the whole region in their development pipelines as of January 2021. Since then, China’s government has announced a 30GW by 2025 deployment target for non-PHES energy storage technologies.

Australia came second, with 7,880MW of planned or in-construction pumped hydro, followed by Indonesia (4,063MW), India (2,780MW) and Japan (2,480MW). The Philippines and Vietnam had smaller 500MW and 1,200MW pipelines respectively. 

10 April 2024
12pm (AEST)
Join Energy-Storage.news and energy storage market experts at GridBeyond for a discussion on the evolving landscape for energy storage in Australia’s National Electricity Market, and the challenges faced in optimising the value of battery assets in an evolving market.

Read Next

March 18, 2024
Construction has kicked off at the largest battery project in Australia to date, with a storage capacity equivalent to the entire country’s fleet of projects in construction at the end of 2022.
Premium
March 14, 2024
The COO of one of the few energy-storage focused lithium-ion gigafactory companies in Europe, Morrow Batteries, talked to Energy-Storage.news about the firm’s go-to-market strategy and what the future holds for Europe’s gigafactory space.
March 13, 2024
Rooftop solar and utility-scale energy storage growth led renewable energy to fulfil almost 40% of Australia’s electricity supply in 2023.
March 13, 2024
Fluence will supply batteries for a 150MW/300MWh battery storage project for SSE Renewables at Fiddler’s Ferry, Warrington, UK.
Premium
March 12, 2024
System integrator Powin is working on a new grid-scale BESS product to compete with increasingly competitive product from China, senior VP Danny Lu told us, while also discussing its Waratah project in Australia and fire safety.

Most Popular

Email Newsletter