Elements Green receives GPS approval for 1.3GWh solar-plus-storage site in Queensland, Australia

LinkedIn
Twitter
Reddit
Facebook
Email
The solar-plus-storage site will be within the proposed Central Queensland renewable energy zone. Image: Elements Green.

UK-headquartered developer Elements Green has received grid connection approval from Powerlink Queensland and the Australian Energy Market Operator (AEMO) for a 1.3GWh solar-plus-storage site in Queensland, Australia.

The developer announced it has received its 5.3.4.A letter from the state-owned network operator and AEMO for its Eurimbula Hybrid Facility.

Elements Green claims this is Australia’s largest solar and battery energy storage project to have received Generator Performance Standard (GPS) approval. It will couple 696MWp of solar PV generation with a 666MW/1,332MWh battery energy storage system (BESS).

The hybrid facility will be located within the proposed Central Queensland renewable energy zone (REZ), approximately 50km southeast of Gladstone. Queensland is set to pursue the development of 12 REZ across the state to support the deployment of 22GW of renewables by 2035.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, with the recent election of the right-wing Liberal National Party (LNP) of Queensland, and several shifts in energy policy, leading to the cancellation of the 120GWh Pioneer-Burdekin pumped hydro project, question marks will be raised as to whether these will all be pursued.

For Elements Green, the receipt of the 5.3.4.A letter marks a vote of confidence in what will be the developer’s first solar-plus-storage project in Australia, with hopes to break ground on the site later this year.

Indeed, the letter grants the approval of performance standards and the System Strength Impact Assessment, as outlined in Clause 5.3.4A of AEMO’s National Electricity Rules.

Toby Roberts, country director of Elements Green Australia, said the project will benefit from “abundant sunshine, a stable grid, and strong regulatory support.”

According to documents submitted to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act, the hybrid facility will be spread across a 1,280-hectare area. The proposal includes the development of an onsite substation and will connect to the National Electricity Market (NEM) via existing 275kV transmission lines.

Development approval for the site was granted by the Gladstone Regional Council in 2018.

Elements Green is the second company to receive a 5.3.4.A letter for a solar-plus-storage site in recent weeks. Indeed, Energy-Storage.news reported on Friday (16 May) that developer Elgin Energy received grid connection approval for its 150MW Elaine solar-plus-storage project, situated in the Central Highlands region of Victoria.

Australia’s rigorous grid codes

Australia has one of the most rigorous grid code certification processes, which is part of AEMO’s GPS approval process, as noted by Energy-Storage.news in recent months.

Tom Best, the COO of Eku Energy, a company that develops, owns, and operates BESS, recently told ESN Premium that the procedure for developers in Australia to connect to the transmission grid and tap into the NEM Frequency Control Ancillary Services (FCAS) and energy trading markets is extremely stringent.

He also noted that it represents one of the longest and costly grid compliance processes among all the markets in which Eku Energy operates.

AEMO’s technicians subject plants to a wide variety of scenarios and ultimately push the plant or its model to the breaking point, which, as Best noted, necessitates project designers conducting numerous studies.

Once this is completed, the process is documented in a Grid Protection Scheme (GPS), which must then receive approval from both the Network Service Provider (NSP) and AEMO before the market operator issues the 5.3.4A letter of compliance.

However, the process does not end with the receipt of the 5.3.4A letter. Since the GPS is formulated based on modelling, any alterations made during the construction phase, such as modifications in plant design or cabling setups that might impact its electrical characteristics, must be updated through a procedure known as R1.

While a project can be awarded a GPS, the R1 process demonstrates that the project meets or surpasses its performance standards as required by AEMO and the network service providers. If these standards are not met, the GPS can be retracted.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 10, 2026
Akaysha Energy’s Waratah Super Battery in Australia briefly reached its full rated output of 850MW on 7 September.
September 10, 2026
The venture-capital-style returns once available in Australia have disappeared, according to panellists at the Battery Asset Management Summit Australia 2026.
September 9, 2026
Ayala’s ACEN Corp has loaned PHP9 billion (US$144 million) to subsidiaries within the group for renewable energy and battery storage projects.
Premium
September 9, 2026
In this interview with ESN Premium, Sahand Karimi of OptiGrid discusses how BESS warranties and constraint management shape trading behaviour.
September 9, 2026
Australia’s 58 grid-scale battery storage systems in the NEM generated a combined AU$28.79 million in estimated gross energy and FCAS revenue.