Australia’s Waratah Super Battery enters planned shutdown amid transformer replacement efforts

LinkedIn
Twitter
Reddit
Facebook
Email

Developer Akaysha Energy has confirmed that the 850MW Waratah Super Battery in Australia will undergo a planned balance of plant shutdown from 20 November to 2 December 2025.

It comes as the BlackRock-backed developer continues to address the aftermath of a catastrophic transformer failure that occurred in October.

The 850MW/1,680MWh battery energy storage system, currently operating at a reduced 350MW capacity, maintains its System Integrity Protection Scheme (SIPS) service requirements, despite transformer issues that have delayed the full commissioning of what was designed to be the world’s most powerful battery storage system.

Estimates suggest the transformer failure could result in total losses between AU$50-80 million (US$32-51 million), according to Dr Tom Harries, partner at NARDAC, a specialist energy and infrastructure broker that provides battery energy storage insurance.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The final loss amount depends on the timing of transformer replacement and whether a delay in start-up coverage applies to the project.

“If the project can replace the transformers in six months, possibly under a delay in start-up cover depending on whether the project has fully gone live or is still in testing, then the loss could be as low as AU$50 million,” Harries told Energy-Storage.news.

“However, this is contingent on securing transformers fairly quickly; otherwise, a much larger claim is likely.”

Main power transformer replacement typically requires extended lead times, with specialised equipment often taking 12-18 months to manufacture and deliver.

However, the transformers were manufactured by an Australian-based company (Wilson Transformer), providing advantages for the diagnostic and rectification process. In doing so, all diagnostic, rectification and re-commissioning activities can be undertaken locally, allowing faster turnaround times and close oversight of the repair process.

The transformer failure represents a significant setback for the BlackRock-owned project, which serves as Australia’s “giant shock absorber for the power grid”.

Located at the former Munmorah coal-fired power station site near Budgewoi, the facility monitors 36 transmission lines in real time and responds within seconds to grid disturbances.

Akaysha Energy CEO Nick Carter described the transformer incident as a “catastrophic failure” in an internal memo, highlighting the severity of the technical issue that has reduced the project’s operational capacity by more than half.

The scheduled shutdown is part of routine maintenance and has been coordinated with AEMO and Transgrid for several months.

It will affect the project’s current 350MW operational capacity during a critical period for Australia’s electricity system. The timing coincides with increasing summer demand patterns and ongoing challenges in managing renewable energy intermittency across the National Electricity Market (NEM).

Akaysha Energy expects the battery storage system’s remaining capacity to return online during 2026, according to a spokesperson.

9 June 2026
Stuttgart, Germany
Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.

Read Next

May 29, 2026
In this Energy-Storage.news roundup, a collection of battery energy storage system (BESS)-related announcements from NeoVolta, Goshe Energy Storage, Frontier Power USA and Stella Energy Solutions, and Prevalon Energy.
Premium
May 29, 2026
Managers of the UK’s largest BESS owner-operator Gresham House Energy Storage Fund (GRID) discussed recent investment news and future strategy this week. 
May 29, 2026
The German network regulator’s decision to maintain grid fee exemptions for battery storage “ensures that billions in private investment remain directed” into the market, Energy-Storage.news has heard.
May 29, 2026
Ausgrid has submitted its 150MW/300MWh Berkeley Vale BESS to the Australian government’s EPBC Act for federal environmental assessment.
May 29, 2026
South Australia’s first Firm Energy Reliability Mechanism (FERM) tender has awarded agreements to six battery energy storage projects totalling 1,334MW and 5,336MWh.