World’s biggest battery storage system comes back online after months of shutdown

LinkedIn
Twitter
Reddit
Facebook
Email

Moss Landing Energy Storage Facility, at 400MW/1,600MWh the world’s biggest battery energy storage system (BESS) project so far, is back online.

Owner Vistra Energy had called a temporary halt to its operation and market participation after battery overheating incidents at both phases of the project.

The 300MW/1,200MWh Phase I, commissioned in December 2020, went out of action after a September 2021 incident, while Phase II’s separate 100MW output and 400MWh of capacity went online a month before that incident, only to be also switched off in February this year.

Vistra said in a statement yesterday (11 July) that a successful restart has been carried out with more than 98% of the total 400MW storing energy and releasing it to California’s CAISO grid. The plan communicated earlier by the company, had been to have it up and running during the first half of this year.

While the company had not responded to an earlier enquiry on progress from Energy-Storage.news last month, yesterday Vistra revealed it had been incrementally beginning to re-energise the battery energy storage system (BESS) in May and June.

The final 2%, or 7MW, will come back online once equipment (replacement batteries and electrical components) arrives on site and the company said it continues to work with regulators and local authorities as restoration work goes on.

A further expansion of the facility is ongoing, the independent power producer (IPP) said. Phase 3 will add 350MW/1,400MWh of capacity and the start of its installation was announced in January. The company has previously said that Moss Landing, at which BESS technology has been installed in the former turbine halls and other parts of a former gas power plant site, has the infrastructure and grid connection capacity to potentially be sized up to 1.5GW/6GWh.

Indeed, California utility PG&E, which is an offtaker for Vistra’s BESS, has also just deployed its own system at Moss Landing, the 182.5MW/730MWh Elkhorn Battery. While Vistra’s Moss Landing project uses LG Energy Solution battery racks, Tesla supplied the full BESS solution to PG&E for Elkhorn.

Batteries themselves were not the cause of the overheating, at least not at Phase 1, according to Vistra’s principal investigation findings published in January.

Instead, a fault-detection system responded to an overheating air-handling unit, triggering sprinklers that “improperly” sprayed water onto battery racks, which had been operating at normal temperature until the spraying occurred.

Vistra’s report also contained a number of corrective actions that the company said it would take.

Moss Landing Energy Storage Facility: Timeline of the story so far

July 2018: Vistra wins offtake contract with PG&E for 300MW Phase 1 of Moss Landing Energy Storage Facility, while Tesla gets contracted to deliver PG&E’s own project at the site. They will be among the first large-scale battery systems with four-hour capacity contracts for resource adequacy.

September 2018: Regulator California Public Utilities Commission (CPUC) approves the contracts.  

December 2020: Vistra brings Phase 1 online

June 2021: LG Energy Solution announced it supplied battery racks to the project.

August 2021: Phase 2 is brought online.

September 2021: Overheating incident brings operation of Phase 1 to a halt.

January 2022: 350MW Phase 3 is announced.

January 2022: Vistra announces findings of preliminary investigation.

February 2022: Phase 2 taken offline after what was described as a similar instance of overzealous sprinkler activation causing problems with a number of battery racks.

April 2022: CPUC approves PG&E’s contract with Vistra for MOSS350, the 350MW/1,400MWh BESS third phase of the project.

May/June 2022: Capacity back online.

Read Next

March 30, 2023
Wärtsilä’s battery energy storage system (BESS) product Gridsolv Quantum has achieved the “best possible outcome” in UL9540A testing.
March 29, 2023
US energy efficiency and renewables company has entered into “strategic relationship” with Australian flow battery provider.
March 29, 2023
National science agency CSIRO has said Australia needs multiple energy storage technologies at massive scale to achieve its transition.
March 28, 2023
Adapting transmission infrastructure and accurately valuing energy storage are the major challenges to deployments in the US today, said panellists on the Keynote discussion at Energy Storage Summit USA today.
March 28, 2023
Cameron Murray talks to industry experts about the physical security risks to battery storage sites, and how the security and insurance aspects of operating BESS sites are evolving.

Most Popular

Email Newsletter