World’s biggest battery storage system comes back online after months of shutdown

LinkedIn
Twitter
Reddit
Facebook
Email

Moss Landing Energy Storage Facility, at 400MW/1,600MWh the world’s biggest battery energy storage system (BESS) project so far, is back online.

Owner Vistra Energy had called a temporary halt to its operation and market participation after battery overheating incidents at both phases of the project.

The 300MW/1,200MWh Phase I, commissioned in December 2020, went out of action after a September 2021 incident, while Phase II’s separate 100MW output and 400MWh of capacity went online a month before that incident, only to be also switched off in February this year.

Vistra said in a statement yesterday (11 July) that a successful restart has been carried out with more than 98% of the total 400MW storing energy and releasing it to California’s CAISO grid. The plan communicated earlier by the company, had been to have it up and running during the first half of this year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

While the company had not responded to an earlier enquiry on progress from Energy-Storage.news last month, yesterday Vistra revealed it had been incrementally beginning to re-energise the battery energy storage system (BESS) in May and June.

The final 2%, or 7MW, will come back online once equipment (replacement batteries and electrical components) arrives on site and the company said it continues to work with regulators and local authorities as restoration work goes on.

A further expansion of the facility is ongoing, the independent power producer (IPP) said. Phase 3 will add 350MW/1,400MWh of capacity and the start of its installation was announced in January. The company has previously said that Moss Landing, at which BESS technology has been installed in the former turbine halls and other parts of a former gas power plant site, has the infrastructure and grid connection capacity to potentially be sized up to 1.5GW/6GWh.

Indeed, California utility PG&E, which is an offtaker for Vistra’s BESS, has also just deployed its own system at Moss Landing, the 182.5MW/730MWh Elkhorn Battery. While Vistra’s Moss Landing project uses LG Energy Solution battery racks, Tesla supplied the full BESS solution to PG&E for Elkhorn.

Batteries themselves were not the cause of the overheating, at least not at Phase 1, according to Vistra’s principal investigation findings published in January.

Instead, a fault-detection system responded to an overheating air-handling unit, triggering sprinklers that “improperly” sprayed water onto battery racks, which had been operating at normal temperature until the spraying occurred.

Vistra’s report also contained a number of corrective actions that the company said it would take.

Moss Landing Energy Storage Facility: Timeline of the story so far

July 2018: Vistra wins offtake contract with PG&E for 300MW Phase 1 of Moss Landing Energy Storage Facility, while Tesla gets contracted to deliver PG&E’s own project at the site. They will be among the first large-scale battery systems with four-hour capacity contracts for resource adequacy.

September 2018: Regulator California Public Utilities Commission (CPUC) approves the contracts.  

December 2020: Vistra brings Phase 1 online

June 2021: LG Energy Solution announced it supplied battery racks to the project.

August 2021: Phase 2 is brought online.

September 2021: Overheating incident brings operation of Phase 1 to a halt.

January 2022: 350MW Phase 3 is announced.

January 2022: Vistra announces findings of preliminary investigation.

February 2022: Phase 2 taken offline after what was described as a similar instance of overzealous sprinkler activation causing problems with a number of battery racks.

April 2022: CPUC approves PG&E’s contract with Vistra for MOSS350, the 350MW/1,400MWh BESS third phase of the project.

May/June 2022: Capacity back online.

Read Next

July 3, 2026
Australia’s 55 grid-scale BESS generated a combined AU$17.98 million in estimated gross energy and FCAS market revenue during June 2026.
July 3, 2026
AGL has delivered a solar and battery microgrid described as “one of the largest privately owned non-mining microgrids in Australia”.
Premium
July 2, 2026
State of charge (SOC) is on the face of it a straightforward measurement for batteries and BESS. But in reality, it’s highly complex and under- or over-reporting still happens in the industry, leading to under-performance and losses in revenue.
July 2, 2026
Singapore-headquartered clean energy developer Vena Energy has raised AU$1.4 billion (US$970 million) in green finance to support 614MW of solar PV capacity and 1,141MWh of battery energy storage systems (BESS) in Australia.
July 1, 2026
Samsung C&T Renewable Energy Australia has submitted the 600MWh Comet Park BESS for federal environmental assessment under the EPBC Act.