Poland: R.Power enlists EPCs for 2.2GWh of BESS, EDF and Eurus, Eiffel and Ergy co-invest in projects

LinkedIn
Twitter
Reddit
Facebook
Email

It’s been a busy week for the large-scale energy storage market in Poland, with projects moved to construction and delivery by EDF Power Solutions & Eurus Energy Europe, Eiffel Investment Group & Ergy, R.Power Renewables, and EDP.

The Polish market is entering a phase of construction and execution as the first 2027-2030 delivery dates for the country’s 2022-2025 capacity market (CM) auctions start to approach. The CM is part of the country’s efforts to secure supply as coal is phased out and more renewables come onto the system.

Battery energy storage system (BESS) projects have won a combined c.5GW of obligations over the four auctions, while the size of those projects is more like 10-20GW. The CM and its 17-year guaranteed revenues is the bedrock of the business case for most (though not all) large-scale projects in Poland.

EDF Power Solutions and Eurus establish JV for Poland project

EDF power solutions, part of the power group EDF, and IPP Eurus Energy Europe have established a JV to build and operate a 120MW/280MWh BESS in Porąbka, Poland.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The project, initially owned and developed by EDF power solutions Polska, will soon start construction and is targeting a commercial operation date (COD) in the second half of 2027.

Eurus said the project was initially owned and developed by EDF power solutions Polska, indicating it has come in at a later date as investor. The firms didn’t mention a CM contract for the project.

It is EDF Power Solutions’ second project in the country after it commissioned a 120MWh system earlier this year. While this is Eurus’ first in the country, it has worked on projects elsewhere in Central Eastern Europe (CEE) region.

Eiffel Investment Group and Ergy to jointly build 46MW/184MWh project

Investors Eiffel Investment Group and Ergy have partnered to invest in BESS projects in Poland, starting with a 46MW/184MWh system in Baczyna.

The project is ready-to-build (RTB) with commercial operations expected to begin in 2028, and it has a CM contract.

Eiffel Investment Group will provide long-term infrastructure investment expertise while Ergy will originate, develop, arrange financing, construct and manage the projects. The pair are looking to acquire other projects in Poland.

They said the project also benefits from support from the European Union under the InvestEU fund. The fund helps mobilise private sector investment in critical industries by providing financing packages, and has funded BESS in Denmark and elsewhere in CEE.

Eiffle has also invested in projects in Romania, in partnership with IPP R.Power, which this week also progressed large projects in Poland.

R.Power enlists EPCs for two Poland BESS, totalling 2.2GWh

R.Power this week announced signing engineering, procurement and construction (EPC) contracts for two more large-scale projects in Poland.

It has enlisted contractor Onde to deliver its Dzięgielewo (300MW/1,200MWh) project and a separate contractor, Esix, to deliver its Gdańsk (250MW/1,000MWh) project. Both projects are expected to come online around the turn of 2027/2028.

R.Power enlisted power firm Axpo for a 10-year optimisation deal, with a floor, for the Dzięgielewo in May this year.

Though R.Power didn’t mention a CM contract for the two projects, it has won 1.7GW/6.3GWh of CM obligations for BESS in Poland, so they are likely to be included in that. It is also open to selling some of those projects, as it did with the 250MW/1GWh Tursko Wielkie BESS to power firm Engie last month.

R.Power is also building a 150MW/300MWh in Jedwabno, Poland (which it financed earlier this year), as well as the 127MW/254MWh Scornicesti project in Romania (the one invested in by Eiffel).

We discussed optimisation, financing and procurement with two of the R.Power team earlier this year at the Energy Storage Summit 2026 in London.

EDP to deploy 8MW/20MWh for logistics firm

Finally, Portugal-headquartered power firm EDP will deploy BESS units totalling 8MW/20MWh for logistics firm CLIP at four separate sites. The BESS will help CLIP increase the efficiency of its electricity consumption management.

Our publisher Solar Media will hold the Energy Storage Summit Central Eastern Europe (CEE) 2026 on 6-7 October in Warsaw, Poland. Use our code ESN20 for a 20% discount on tickets.

6 October 2026
Warsaw, Poland
The Energy Storage Summit Central Eastern Europe is set to return in September 2025 for its third edition, focusing on regional markets and the unique opportunities they present. This event will bring together key stakeholders from across the region to explore the latest trends in energy storage, with a focus on the increasing integration of energy storage into regional grids, evolving government policies, and the growing need for energy security.

Read Next

July 24, 2026
ESS Tech Inc is deploying sodium-ion BESS in the US with Juniper Energy, while CATL deploys its sodium-ion technology in Eastern Europe with Solarpro.
July 24, 2026
In this news roundup, Grenergy, MaxSolar and Saft, and Amarenco have made significant advancements on BESS projects in Spain, Germany, and France.
July 23, 2026
Germany will have its first capacity market (CM) auction in September this year, following confirmation from the country’s energy regulator.
July 22, 2026
Activity in Italy’s grid-scale market is accelerating, with Sonnedix and the Strioga Family Foundation acquiring projects totalling over 1GWh combined, while BNZ and RWE have ordered BESS from Sungrow and LONGi respectively totalling 540MWh.
July 22, 2026
Delta Capacity has brought online the Nordic region’s biggest project to date and has acquired another project that would be almost twice the size.