R.Power and Axpo agree optimisation deal with floor for 1.2GWh Poland BESS

LinkedIn
Twitter
Reddit
Facebook
Email

IPP R.Power has enlisted power firm Axpo to optimise a 300MW/1,200MWh BESS in Poland, one of the largest such deals seen in Continental Europe.

Axpo will provide the full scope of optimisation services for the 4-hour battery energy storage system (BESS) in Dzięgielewo, east-central Poland, set to come online in 2028. The agreement runs for 10 years from the start of commercial operations.

It guarantees a minimum level of revenues for R.Power via a ‘floor’, helping bankability for the project, further aided by Axpo’s strong balance sheet (it is Switzerland’s largest electricity producer).

The companies had previously agreed a similar deal for a 150MW/300MWh BESS in Poland, announced in January this year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Axpo Polska head of origination Krzysztof Włodyga, commented: “A key challenge was scaling solutions to 300MW and refining them in the context of rapidly evolving operational and regulatory standards.”

The two companies have also previously signed solar PPAs. R.Power is active across numerous markets in solar and storage, see our recent video interview with two of its executives at the Energy Storage Summit 2026 in London here.

R.Power has 1.7GW/6.3GWh of BESS in Poland with capacity market (CM) contracts, won in annual auctions over the last few years including the most recent CM auction in late 2025. That auction saw the capacity awarded to BESS fall for the first time, following a big de-rating cut for the technology in order to favour gas.

The CM is the bedrock of the business case for large-scale BESS in Poland, helping drive gigawatt-hours of development and construction activity there. Projects and portfolios were progressed in the past two months alone by Green Capital, Tavion and Low Carbon.

Read Next

November 20, 2026
Another BESS Industry Buzz, looking at what people are discussing in the industry plus some of the most notable quotes from the RE+ trade show, which concluded yesterday.
November 17, 2026
The latest edition of PV Tech Power is available to download, full of exclusive content for the downstream solar PV and BESS industries.
Premium
November 17, 2026
There is limited benefit to questioning every decision made, but operators should be hands on with their optimiser, industry sources said at the Battery Asset Management Summit UK & Ireland 2026 last month.
Premium
November 13, 2026
Floors are increasingly the offtake structure of choice in the UK market, and the contracting for them is beginning to standardise, industry experts said.
November 12, 2026
Analysis of optimiser performance in the Dutch electricity market highlights the need to separate claims and forecasting from realistic outcomes, writes Omer Bumin of trading infrastructure software company Powerlys.