Northland Power secures financing for 80MW/160MWh BESS in Alberta, Canada

April 14, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

IPP Northland Power has achieved financial close for the 80MW/160MWh Jurassic battery energy storage system (BESS) project in Cypress County, Alberta, CA.

Northland says that all necessary financing has been secured, and construction will start soon.

The Jurassic BESS has signed construction agreements and a 15-year fixed-price capacity contract. The IPP expects the BESS to be commercially operational in late 2026.

Northland estimates the total cost at approximately CA$120 million (US$85.84 million). Construction costs will be funded through non-recourse project-level financing, existing cash, and available liquidity. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Jurassic BESS is expected to contribute approximately CA$15 million of annual adjusted earnings before interest, taxes, depreciation and amortisation (EBITDA).

The BESS will also be the largest in the province of Alberta.

According to the Canada Energy Regulator (CER), Alberta was the largest producer of crude oil in the country in 2023.

The majority of the province’s crude oil production comes from the oil sands in northern Alberta.

Peer-reviewed American academic journal, Science, found in a 2024 report that air pollution from the Athabasca oil sands in Alberta was 1,900% to over 6,300% greater than what the oil sands industry reported.

Alberta has, however, seen its fair share of renewable energy projects and investments.

In 2023, the Canadian Renewable Energy Association (CanREA) noted that Alberta saw 92% of new wind, solar and energy storage capacity connected to the country’s grid.

This included 130MW of energy storage. Utility-scale energy storage developer Enfinite installed 100MW, part of its nine-project Alberta portfolio.

Energy-Storage.news reported on the increased applications Alberta received for renewable energy projects in 2024 (Premium access), following its 7-month moratorium on 1MW+ green-energy developments, which was lifted in the first quarter of that year.

Toronto, CA-headquartered Northland was founded in 1987 and claims to now own or have an economic interest in 3.2GW of gross operation generating capacity, with 2.4GW under construction.

The company has a 72% stake in the 250MW/1,000MWh Oneida BESS (Premium access), Ontario’s flagship BESS project.

That project is still under construction and expected to be completed sometime this year.

Northland also owns Jurassic Solar+, which is in late-stage development and will be paired with the Jurassic BESS project.

The solar portion of the project has a 220MWac capacity.

15 April 2026
Milan Marriott Hotel, Italy
Solarplus Europe 2026 marks the evolution of Europe’s longest-running solar conference, reflecting the industry’s transition from standalone PV to fully integrated solar-plus-storage and hybrid energy systems. Taking place in Milan, the Summit will unite developers, investors, policymakers, and technology leaders to explore how Europe can deliver firm, flexible, and bankable renewable power at scale. With a sharp focus on system integration, storage deployment, hybrid project design, and market-ready business models, Solarplus Europe provides the platform for shaping the next phase of the continent’s solar and clean power build-out.
9 June 2026
Stuttgart, Germany
Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.
23 June 2026
Toronto Congress Centre, Canada
Battery Asset Management Summit is a globally recognized Summit series focused exclusively on the operational, commercial, and technical performance of utility-scale battery assets. In 2026, the Summit arrives in Canada for the first time, at a pivotal moment for the country’s energy storage market and wider energy transition.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.

Read Next

April 7, 2026
Quebec-based IPP Boralex and Six Nations of the Grand River Development Corporation (SNGRDC) have announced the closing of a CA$202 million (US$145.12 million) financing for a 125MW/500MWh battery energy storage system (BESS) in Oxford County, Ontario, CA.
Premium
April 7, 2026
The project represents a US$128.6 million investment and is scheduled to begin construction this year, with commercial operations commencing in December 2026.
April 7, 2026
IPP Neoen will start construction on large-scale BESS projects in France and Japan in the coming months.
Premium
April 3, 2026
How do you ensure quality and performance and mitigate risk when buying BESS equipment? Expert speakers from consultancies, analytics firms and independent power producers discussed the topic in a recent panel discussion.
Premium
April 2, 2026
The Reno Planning Commission, in Nevada, US, recommended approval for a conditional-use permit for the 200MW Trego Grid energy storage project on 4 March.