US utility Southern California Edison (SCE) has classified energy storage as an “eligible preferred resource” in a 100MW request for offers (RFO) it has issued to acquire renewable energy, capacity and load reduction from new sources.

The RFO serves as the second action launched to support SCE’s Preferred Resources Pilot (PRP) in central and southern Orange County and is looking for 100MW for delivery in 2018.

Caroline McAndrews, director of SCE’s Preferred Resources Pilot, said: “Now in its second full year, this pilot is a real-world test where SCE is exploring how cleaner-energy resources can help maintain or improve electric service reliability in a densely populated area.”

Preferred resources for the RFO include renewable distributed generation, demand response, energy storage and renewable generation linked with energy storage.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Projects that stand in line with the RFO requirements can take part in the competitive bidding process, while SCE has scheduled an in-person bidder’s conference on Oct. 7 in the Orange County area.

“The grid of the future will have a mix of these preferred resources providing reliable and affordable service to our customers while reducing or eliminating the need to build new gas-fired plants,” the director of the Preferred Resources Pilot for SCE, Carol McAndrews, said.

“Now in its second full year, this pilot is a real-world test where SCE is exploring how cleaner-energy resources can help maintain or improve electric service reliability in a densely populated area. This second RFO helps us prepare for the future and keeps us moving forward in obtaining the cleaner resources needed for this innovative project.”

The utility, along with California’s other two investor-owned utilities (IOUS), also issued its Distribution Resources Plan for approval to the state Public Utilities’ Commission (PUC) earlier this year, through which the utilities and the state are seeking to migrate towards more distributed and therefore less centralised energy networks, with solar and storage already playing a major part.

Additional reporting by Andy Colthorpe.

Read Next

October 2, 2026
Outgoing California Governor Gavin Newsom recenty addressed approximately 1,200 bills, including several energy storage and solar related bills that were either approved or vetoed.
October 1, 2026
Energy-Storage.news spoke with Noemí Gallardo, Commissioner at the California Energy Commission (CEC), at the US Solar & Storage Finance event in Garden Grove, California, about the growth of BESS within the state.
September 24, 2026
Market research firm Wood Mackenzie stated that data centre buildout is uplifting the US battery energy storage system (BESS) outlook across all segments.
September 22, 2026
Residential battery energy storage systems (BESS) across California discharged more than 580MW of peak power to the state’s grid on the evening of 9 September 2026 via a Tesla-Sunrun VPP.
September 22, 2026
Utility PG&E has selected six new California microgrid projects for a US$30 million investment, while Massachusetts’ Department of Energy Resources is awarding US$40 million across 36 BESS projects.