Largest BESS in Czech Republic commissioned, supplied by CATL-backed CNTE

LinkedIn
Twitter
Reddit
Facebook
Email

The largest grid-scale battery energy storage system (BESS) project in the Czech Republic has gone online, supplied by a company invested in by lithium-ion OEM CATL. 

The Modlany Energy Park combines 42.7MW of solar PV with a 37.95 MW/41.7 MWh BESS, the largest in the country. It takes the crown from a 30MW system commissioned by IPP Decci Group in 2024 

BESS supplier Contemporary Nebula Technology Energy (CNTE) provided 11 of its CNTE STAR T-285 liquid-cooled containers, each rated at 3.45MW/3.793MWh. The STAR T is designed for 1P charging and discharging and 1-4-hour durations. 

CNTE was founded by Huang Shilin, who is the co-founder and former vice chairman of CATL, which holds a 20% stake in CNTE. Shilin left his position at CATL in 2022, but remains a significant shareholder in CATL. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Engineering, procurement and construction (EPC) for the Modlany project was provided by contractor Greenbuddies, which announced its completion in May. It is located on a former mining site. 

The project will provide fast-response frequency regulation and grid balancing services to the Czech energy system, as well as trade in the energy market. 

It appears to be owned by the Katemo Group, which says on its website that its BESS capacity could be increased in future to 130MWh. The project as a whole is the result of CZK1.2 billion (US$57 million). 

The largest BESS player in the Czech Republic (also known as Czechia) that we are aware of is Second Foundation. The energy trader-turned project owner claims to be commissioning 307MW/620MWh of BESS capacity this year. 

Like numerous other countries in Southern Europe and Central and Eastern Europe (CEE), the grid-scale storage market has been kickstarted by a grant scheme using EU funds. The European Commission approved Czechia’s last year, which will put CZK7 billion in direct grants to projects totalling at least 1,500MWh.

6 October 2026
Warsaw, Poland
The Energy Storage Summit Central Eastern Europe is set to return in September 2025 for its third edition, focusing on regional markets and the unique opportunities they present. This event will bring together key stakeholders from across the region to explore the latest trends in energy storage, with a focus on the increasing integration of energy storage into regional grids, evolving government policies, and the growing need for energy security.
3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 2, 2026
India’s Union Cabinet has approved US$ 19.3 billion Green Energy Corridor, including US$ 5.2 billion for 50GWh BESS through FY2032-33.
October 2, 2026
Outgoing California Governor Gavin Newsom recenty addressed approximately 1,200 bills, including several energy storage and solar related bills that were either approved or vetoed.
October 2, 2026
Renalfa IPP and Eurowind have brought a large-scale hybrid renewables project, featuring 242MWp of solar PV and 773MWh of battery storage, into commercial operation in Bulgaria.
October 2, 2026
Northland Power has closed financing on two large-scale battery energy storage system (BESS) projects in Poland.
September 30, 2026
Spain’s recent proposal for data centres could be the catalyst the country’s energy storage market has been waiting for, argues Ignacio López Martín from developer Capflex Energía.