Canadian Solar will retrofit 300MWh of batteries at Goldman Sachs’s Mustang Solar plant, California

LinkedIn
Twitter
Reddit
Facebook
Email
Recurrent Energy brought Mustang Solar online in 2016 and it was sold to Goldman Sachs Renewable Power in 2019. Image: Recurrent Energy.

Vertically integrated solar PV company Canadian Solar will install 75MW / 300MWh of battery energy storage at an existing California solar power plant owned by Goldman Sachs Renewable Power.

Canadian Solar’s project development subsidiary Recurrent Energy actually developed and then sold the 100MW / 134MWp Mustang Solar project in California’s Kings County to the renewable power group of Goldman Sachs Asset Management. The project reached commercial operation in 2016 before its sale last year. The battery storage system will begin construction early in 2021 for completion by the second half of next year.

In August, as reported by Energy-Storage.news, Canadian Solar executives including CEO and chairman Dr Shawn Qu had said that the company saw “significant growth opportunities in the solar-plus-storage market” as it reported its latest financial results. This growth extended to Canadian Solar claiming an energy storage project backlog and pipeline totalling 4,683MWh as of the end of June 2020, which was double what it reported for the previous quarter.

The growth, Canadian Solar said, would be driven by dynamics including “declining battery storage costs, higher capacity needs and accelerating retirements of fossil fuel power plants,” with the company touting that its vertically integrated business model which includes PV module manufacturing and project development made it an ideal candidate to expand its presence in the solar-plus-storage space.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Project to include four-hour lithium iron phosphate battery storage system

Canadian Solar will provide a 75MW, four-hour duration energy storage system based on lithium iron phosphate (LFP) battery technology to the Mustang Solar plant. While the company said in August that it will be seeking to retain a minority stake in projects it develops in order to generate cashflow from additional revenue streams such as power sales and operations and maintenance (O&M), this does not appear to have been the case for the Mustang Project. Canadian Solar’s contract with Goldman Sachs Renewable Power does however include provision of all future O&M and battery augmentation services as well as performance guarantees relating to metrics including capacity and safety.

Off-takers of electricity from the plant are two California Community Choice Aggregator (CCA) groups, Sonoma Clean power and Marin Clean Energy. In 2018, this site reported that two other CCAs, Monterey Bay Community Energy (MBCE) and Silicon Valley Clean Energy (SCVE) signed deals with Canadian Solar-owned Recurrent Energy for Slate, a 150MW California solar farm paired with 180MWh of battery storage after the community energy groups had sought out lowest-cost offers from providers. Regular readers of this site will note that numerous other California CCAs, which allow customers in investor-owned utility (IOU) services areas to band together and select their energy providers, have also stepped up their activities in buying power from large-scale, four-hour duration solar-plus-storage plants in recent months and years.

In another related example, in late August this year, Goldman Sachs Renewable Power acquired another 100MW solar plant with 50MW of battery storage under development in California’s San Bernadino County for which another CCA, Clean Power Alliance, has a 15-year power purchase agreement (PPA) to buy power from. Yesterday, Energy-Storage.news reported that a group of eight CCAs have joined forces to seek up to 500MW of long-duration energy storage resources.

8 September 2026
Barcelona, Spain
Battery & Energy Storage Tech Europe (BESTE) is Europe’s industrial scaling platform for stationary and industrial battery applications — not EVs. Taking place 8–9 September 2026 at Fira de Barcelona, BESTE brings together utilities, IPPs, energy-intensive industries, data centres, ports, rail, maritime, defence and aerospace OEMs — all deploying or integrating battery storage at scale. Over 100 companies already confirmed — including EDP Renewables, Acciona, Endesa, Naturgy, Neoen, Galp, Basquevolt and Veolia — alongside 40+ expert speakers and international institutional support from BEPA, BVES, LDES and Volta Foundation. Where Europe’s battery & ES ecosystem turns projects into reality.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

July 31, 2026
Thermal energy storage (TES) technology provider Antora Energy has closed a US$550 million Series C funding round to accelerate deployment of its thermal battery storage systems for industrial facilities and data centres in the US.
July 31, 2026
Environmental services company Veolia has been selected to operate and maintain a 350MW microgrid to power an AI data centre campus in New Albany, Ohio, US, which includes a 430MWh BESS.
July 30, 2026
Infrastructure and construction company Aecon Group has executed an agreement with Ontario’s Independent Electricity System Operator (IESO) for the 150MW/1,200MWh Simcoe energy storage project in Norfolk County, Ontario.
July 30, 2026
IPP Eolian has begun construction on Flint Grid, a 200MW/1.06GWh energy storage project in Jersey Township, Licking County, Ohio, US.
Premium
July 30, 2026
How do Chinese OEMs respond to evolving customer requirements and new risks that come with business outside their home market? We sat down with executives from Rept Battero at Intersolar in June to discuss.