50MW largest battery storage system in Northern Ireland switched on

November 26, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Drumkee battery storage project in Northern Ireland. Image: Gore Street.

A 50MW battery storage site in Northern Ireland, UK, has been energised by developer Low Carbon and investment fund Gore Street Energy Storage Fund.

The lithium-ion project, located at Drumkee, County Tyrone, is being lauded as the country’s largest energy storage project and is to serve the Single Electricity Market. It was completed on time, the two companies said, despite the closure of the site for several weeks during the COVID-19 pandemic as well as social distancing measures being needed when the site reopened.

A second 50MW project – Mullavilly – is expected to be energised in December, with both projects to be commissioned and operational in Q1 2021.

To read the full version of this story visit Solar Power Portal.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Read Next

Premium
November 28, 2025
The Township Board of Oshtemo in Michigan has voted in favour of enacting a one-year moratorium on the approval of any new BESS facilities. 
November 27, 2025
A joint venture (JV) between EDF and developer AME has begun construction of large-scale battery and solar photovoltaic (PV) projects in Chile, with 2GWh storage capacity.
November 27, 2025
The Western Australian government has launched the first stage of an Expression of Interest (EOI) process for a 50MW/500MWh vanadium flow battery energy storage system (VBESS) in Kalgoorlie.
November 26, 2025
Mayor of Greater Manchester Andy Burnham marked the commencement of construction at Highview’s 300MWh liquid air energy storage facility.
November 24, 2025
Developer Akaysha Energy has confirmed that the 850MW Waratah Super Battery will undergo a planned balance of plant shutdown from 20 November to 2 December 2025.