Grid-stabilising battery park goes online in northern Germany

September 18, 2014
LinkedIn
Twitter
Reddit
Facebook
Email

A large scale ‘battery park’ has gone online in West Meklenberg, Germany, designed to stabilise grid frequency in an area where a large amount of power generation comes from wind and other renewable energy.

The battery power plant has a rated power output of 5MW and a capacity of 5MWh and is fully automated. It was built by renewable energy and battery system specialist Younicos, with lithium-ion cells supplied by Samsung SDI. The project has been delivered for the regional subsidiary of utility company WEMAG.

WEMAG’s grid has around 800MW of renewable energy capacity installed, which generated around 80% of the energy used in the company’s serviced grid area. According to Younicos, the utility expects this figure to rise to 100% this year. The capacity and output of the park can be doubled to 10MWh and 10MW, respectively.

Germany’s vice chancellor Sigmar Gabriel (second from left), who is also economy and energy minister, at the opening of the park on Tuesday, pictured with younicos executives and local minister Erwin Sellering. Image: younicos
At present the West Meklenberg battery park houses 25,600 lithium-manganese-oxide cells, connected to the grid by medium voltage transformers, capable of boosting the current from 480v up to 20kv and back again. Younicos’ software drives the system, controlling the interaction of batteries between each other and with the grid, as well as ensuring the batteries are suitably charged, both to offer enough capacity to perform its required tasks and to regulate charging to optimise battery life. The system will be housed in a purpose- built hall next to a 110kv substation and will be connected to both the local grid and the 380kv high voltage transmission grid.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Younicos claims the 5MW system can compete with a 50MW gas turbine in frequency regulation markets. This will be put to the test as the commercialised system will participate in frequency regulation markets, as it balances the discrepancies between production and consumption of energy.

Younicos was contracted last year to install a large-scale battery test project in Leighton Buzzard, England with a 6MW capacity and was also awarded a tender to install a similar, 1MW/1MWh project on the Italian island of Sardinia. Each project also uses Samsung SDI cells.

The park houses 25,600 Samsun SDI cells, which are guaranteed for 20 years by the manufacturer. Image: younicos

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.

Read Next

March 27, 2026
Iberdrola has added its 360MWh Broadsound battery energy storage system (BESS) to AEMO’s Market Management System (MMS).
Premium
March 26, 2026
BESS fund manager Gore Street Capital’s director of asset management Daniel Sherlock-Burke recently discussed the work it is doing around capturing and making use of its huge quantities of operational data.
March 26, 2026
Transgrid has shortlisted nine utility-scale battery storage projects, totalling up to 2GW, to provide critical system strength services.
March 25, 2026
AU$2bn deal secures Boyne smelter to 2040+ with 600MW+ battery storage firming renewables for Rio Tinto’s aluminium production in Queensland.
March 24, 2026
Envision Energy’s director of energy storage solutions, Michael Koller, speaks with Energy-Storage.news at Energy Storage Summit 2026 in London, UK.