Germany sets September date for first capacity market auction

LinkedIn
Twitter
Reddit
Facebook
Email

Germany will have its first capacity market (CM) auction in September this year, following confirmation from the country’s energy regulator.

The Federal Network Agency (Bundesnetzagentur or BnetzA) announced the launch of the country’s first tender to guarantee security of supply this week (21 July), enabled under the Electricity Supply Security and Capacity Act (StromVKG).

The bid for deadlines as part of the first tender is 11.59 pm on 8 September, 2026. The tender is open to ‘facilities that can reliably provide electricity over an extended period’.

It didn’t name specific technologies, but in a CM that would typically apply to firm generators such as gas and nuclear as well as battery energy storage systems (BESS).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Capacity markets have been fertile ground for BESS in the UK, Italy, Belgium and Poland. Alongside Germany, Spain is also launching one.

The contracts will be 15-years long, BnetzA said.

“With this law, the legislator has created a framework to ensure that the electricity market will continue to have sufficient secured capacity in the future. This is of paramount importance for security of supply and safeguards against periods when too little electricity is generated from renewable energy sources ,” said Klaus Müller , President of the Federal Network Agency.

The projects must meet specific requirements regarding their location and technical specifications, such as providing instantaneous reserve for grid stability, even during periods of inactivity.

The payment will be determined by the auction. It will prioritise projects in the northern part of Germany’s grid.

A total of 4.5GW of capacity will be tendered for the first bidding round on September 8, 2026. That is including a de-rating factor, which sets a maximum portion of a project’s capacity that can be bid in, to reflect that technology’s reliability in providing CM services. It is typically highest for gas and other dispatchable generation, followed by BESS.

Though the figure for BESS has been a point of controversy in recent years, in Poland for example.

The maximum price in the first auction will be €244,000 (US$278,000) per megawatt of de-rated capacity.

The winners in the first auction will be announced on 3 November, 2026, and the second bidding deadline will be announced on 10 November, 2026.

The announcement of the second bidding deadline for long-term capacities will take place on November 10, 2026.

The CM and its potential for BESS was discussed at the Energy Storage Summit at the Battery Show Europe, hosted by Energy-Storage.news publisher Solar Media and co-located with parent company Informa’s The Battery Show Europe, in Stuttgart at the start of June.

You can see the steps to bid on the BnetzA website here.

The auction deadline will be one week before the Energy Storage Summit Germany, held in Berlin on 15-16 September, a separate event. Use our code ESN20 for a 20% discount on tickets.

15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.
2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

July 23, 2026
Spain has awarded €165 million to seven pumped hydro storage projects totalling around 2.1GW/21GWh, while Portugal has set a target of 1.4GW of new pumped hydro capacity by 2040.
July 22, 2026
Activity in Italy’s grid-scale market is accelerating, with Sonnedix and the Strioga Family Foundation acquiring projects totalling over 1GWh combined, while BNZ and RWE have ordered BESS from Sungrow and LONGi respectively totalling 540MWh.
July 22, 2026
With the Energy Storage Awards 2026 entry deadline less than two months away, we speak to four judges to hear what they are looking for from successful entrants.
Premium
July 22, 2026
BESS deployments in Europe are growing exponentially year-on-year, but is asset management, operations & maintenance (O&M) and data given enough priority? A data executive from BayWa r.e. discussed the topic.
July 21, 2026
Return and Engie have agreed a long-term BESS toll in Spain while EnBW and Zelestra have finalised one in Italy, totalling 55MW and 300MW of capacity respectively.