Geothermal company Ormat buys 80MWh ‘world record’ California energy storage facility

July 27, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Image: AltaGas.

The 20MW / 80MWh Pomona battery energy storage facility, in operation in California since a fast-track process brought it online in partial response to the 2015 Aliso Canyon gas leak, has been bought by Ormat Technologies.

Ormat Technologies announced last week that its affiliate company Ormat Nevada Inc closed the transaction to acquire Pomona from AtlaGas Holdings for US$47 million total consideration, which it said was net of working capital and other adjustments worth around US$3.1 million. Geothermal and recovered energy generation company Ormat said this brings its energy storage portfolio to 73MW / 136MWh of existing assets in operation.

Ormat has been developing as well as acquiring energy storage assets for some time, to add to a 933MW generation portfolio, while the company claims to have engineered, manufactured and constructed 3,000MW gross capacity of power plants to date, which are either under its ownership or were projects executed for utilities and developers in a number of different countries.

The company’s emphasis on energy storage appears to have stepped up not only in response to commercial opportunities for battery projects, but more recently also has been seen by Ormat as a means to offset a slowdown in its other key industry segments. In late June, Ormat Technologies then-CEO, Isaac Angel, said that there had been a decrease in the company’s product backlog “affected by the continuation and increasing severity of the COVID-19 global pandemic”. A “significant product sale contract in the coming months in a different market,” was no longer expected.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“In light of this current situation, we are continuing our efforts to expand and expedite our growth in the electricity segment and energy storage segment,” Isaac Angel had said, before stepping down as CEO at the beginning of July.

Last week, new chief executive officer Blachar said that the Pomona acquisition “is an important addition to our energy storage segment, and it strengthens our activity in the California market, which is the largest and most attractive market in the US for renewables in general and for energy storage in particular”.

Blachar called the energy storage market “one of the most rapidly growing parts of the energy sector” and said Ormat “continues to expand its presence and capabilities” in the sector. Ormat began its move into the segment with the purchase of energy storage and demand response project developer Viridity Energy in 2017, while its most recent own project to come online was the 10MW Rabbit Hill battery system in Texas, which went into commercial operation providing ancillary services and energy optimisation in April.

Pomona: A ‘world record’ fast-track deployment back in 2016

After the four month-long gas leak in October 2015 brought some of California’s energy system to suffer weeks of blackouts, then-Governor Jerry Brown had declared a state of emergency. The shortfall of capacity available resulted in two of its investor-owned utilities, San Diego Gas & Electric and Southern California Edison, running an expedited process to get more than 100MW / 250MWh+ of energy storage online by the end of January 2017 at the latest.

Pomona was one of those systems, brought online under the ownership of infrastructure company AltaGas at one of its natural gas sites and designed, delivered, manufactured, installed and commissioned by turnkey storage systems and software provider Greensmith Energy – now part of Finnish integrated energy solutions company Wärtsilä. At the time it went into operation, just before the end of 2016, Greensmith claimed that the four months it took from conception to switch-on was an industry record.

It has been in commercial operation since 31 December 2016 under a 10-year resource adequacy agreement with Southern California Edison, guaranteeing that energy will be available to the utility as needed but has also joined ancillary services and energy markets run by the California Independent System Operator (CAISO).

“Energy storage resources play a key role in achieving California’s goal to have 100% of its electricity come from carbon-free resources by 2045, by replacing natural gas generators and facilitating massive absorption of renewable energy resources,” Ormat Technologies CEO Doron Blachar said.

“As such, storage is a key part of the energy transformation, and Ormat continues to utilise its expertise, resources, and access to capital to build presence within the energy storage sector, in key target markets, including California, and continues its evolution into a leader in renewable energy.”

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!

Read Next

Premium
January 22, 2026
Foreign entity of concern (FEOC) restrictions and the scheduled Section 301 tariff increase to 25% on Chinese-origin battery energy storage systems (BESS) went into effect on 1 January 2026.
Premium
January 22, 2026
Saudi Arabia and the UAE have emerged as two of the world’s most prominent energy storage markets, with mega-scale projects announced and moved forward at a staggering pace over the last two years. But what does the next phase look like?
January 21, 2026
Virginia’s recently proposed legislation to significantly increase energy storage requirements coincides with unprecedented electricity demand growth in the state, largely driven by data centres.
January 19, 2026
FranklinWH and ConnectDER have had their respective battery and electric meter technologies enrolled into programmes in Arizona expected to accelerate the take-up of home batteries for virtual power plants (VPPs).
Premium
January 19, 2026
US-based iron-sodium battery manufacturer Inlyte Energy has successfully completed a factory acceptance test of its first field-ready battery at its facility near Derby, UK, witnessed by representatives from US utility Southern Company.