Greensmith Energy sets record for quickest delivery with first commissioned Aliso Canyon ESS

January 30, 2017
LinkedIn
Twitter
Reddit
Facebook
Email

Energy storage software and service provider Greensmith Energy has completed and connected its 20MW energy storage system at the AltaGas Pomona Energy Facility in California, in response to the four-month long gas leak at Aliso Canyon, California.

The leak caused power outage concerns, with government officials initiating an emergency storage tender in response.

Greensmith’s project set what it claims to be an industry record for its rapid turnaround of the design, integration and installation of the system in under four months. The system constitutes North America’s largest battery storage facility, comprised of 12,240 lithium-ion batteries in 1,020 racks. It can deliver 80MWh of electricity during peak periods of energy demand to power around 15,000 homes over four hours each day, according to AltaGas.

“With over 50 system deliveries in the last five years, Greensmith has worked not only to advance technology but accelerate time-to-market for grid-scale energy storage systems – with a 100% safety record,” said John Jung, president and CEO of Greensmith.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Aliso Canyon was a particularly exciting opportunity as it demonstrated our ability to partner with AltaGas and leverage our major OEM relationships to deliver the world’s largest and most complex energy storage systems safely and reliably. We are honoured to be part of this landmark project in California in support of an energy leader, AltaGas.”

“This project had a very tight construction and delivery time frame given the sheer size of the project,” said Jim Murphy, CFO & COO of Greensmith. “We worked seamlessly with our tier one supply chain and established ecosystem to deliver this benchmark project on time. Our system-wide expertise and deep integration experience was paramount to the successful delivery of this installation.”

The Aliso Canyon gas leak posed a new opportunity for US energy storage, with as much as 1.8GW of new storage – mostly from lithium-ion batteries – expected to come online by 2021, in response, according to GTM Research.

Greensmith’s and AltaGas’ project will join storage projects from the likes of Tesla, General Electric and AES, who also committed to procuring storage to help with power and grid concerns.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 26, 2026
esVolta has closed a US$139.6 million project financing package with MUFG Bank for its 300MWh Boxcar energy storage project in Texas, US.
March 25, 2026
American Battery Factory (AFB) has secured offtake agreements for 4.5GWh of its initial 5.5GWh US factory output.
Premium
March 25, 2026
As battery energy storage systems (BESS) and electric vehicle (EV) infrastructure expand in the US and Europe, a clear contrast is becoming evident in their market growth.
March 24, 2026
The legislative body of Nebraska, US, has advanced a bill to clarify and expand the state’s use of battery energy storage systems (BESS).
March 23, 2026
The New Jersey Board of Public Utilities (NJBPU) has selected developer and IPP Elevate Renewables’ 600MWh battery energy storage system (BESS) for development in Ridgefield, New Jersey, US.