Genex achieves contractual close for 100MWh Queensland battery project

LinkedIn
Twitter
Reddit
Facebook
Email
Genex solar farm in Kidston, Queensland, close to the site of the 2GWh PHES plant the company has under construction. The 50MW PV facility pictured is being expanded to 270MW to integrate with the pumped hydro. Image: Genex.

Clean energy developer Genex Power has “secured the final piece” of its project finance package for the 50MW/100MWh Bouldercombe Battery Project (BBP) in Queensland, Australia. 

Genex made an announcement to the Australian Securities Exchange (ASX) this morning. Having received firm commitments to a AU$40 million (US$29 million) capital raise to fund the project, it has now achieved contractual close for the standalone battery energy storage system (BESS). 

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The announcement comes just two days after Energy-Storage.news reported that Genex had agreed a AU$35 million debt finance facility for BBP from specialist project finance fund manager Infradebt under a 12-year term.

Tesla will supply 40 of its Megapack grid-scale battery storage units to the project and the US tech company’s Autobidder trading and bidding platform will control its market-facing activities. 

Genex said the AU$40 million institutional placement, alongside the Infradebt loan, will go towards project construction costs as well as repay an existing debt facility to Australia’s national Clean Energy Finance Corporation and provide further working capital. 

“I am delighted to announce today the final piece for the project financing of the Bouldercombe Battery Project, being the completion of a AU$40 million institutional placement,” Genex Power CEO James Harding said, thanking the company’s existing institutional shareholders and welcoming new ones. 

“In acknowledgement of this support, I am pleased to confirm the launch of a AU$10 million Share Purchase Plan to allow our retail shareholders to participate in the capital raising on similar terms to investors under the institutional placement.”

Bouldercombe, along with Genex’s large-scale pumped hydro energy storage (PHES) plant under construction at Kidston, also in Queensland, “will add significant upside exposure for shareholders when it commences operation,” scheduled for mid-2023, Harding said. 

Read Next

March 4, 2024
A 150MW battery energy storage system (BESS), to be deployed along with 373MW of solar PV as part of the Cleve Hill Solar Park project, has reportedly been rejected by the local planning authority in the UK.
March 1, 2024
London Stock Exchange-listed battery storage investment firm Harmony Energy Income Trust (HEIT) has predicted that it can generate “attractive returns” despite the ongoing woes in battery energy storage revenues in the GB market.
Premium
March 1, 2024
Italy grid-scale energy storage market opportunities unlike anywhere else, but many challenges and uncertainties around the different revenue streams remain, including the upcoming MACSE capacity market auction.
Premium
February 29, 2024
We hear from industry sources about why we’ve seen a flurry of investors acquiring energy storage developer-operators in the UK and Germany, Europe’s two largest markets by BESS deployments.
February 29, 2024
Fluence has been issued the required Notice to Proceed on a battery storage project in Australia, which will provide inertia services via the system’s advanced inverter equipment.

Most Popular

Email Newsletter