Genex solar farm in Kidston, Queensland, close to the site of the 2GWh PHES plant the company has under construction. The 50MW PV facility pictured is being expanded to 270MW to integrate with the pumped hydro. Image: Genex.

Clean energy developer Genex Power has “secured the final piece” of its project finance package for the 50MW/100MWh Bouldercombe Battery Project (BBP) in Queensland, Australia. 

Genex made an announcement to the Australian Securities Exchange (ASX) this morning. Having received firm commitments to a AU$40 million (US$29 million) capital raise to fund the project, it has now achieved contractual close for the standalone battery energy storage system (BESS). 

The announcement comes just two days after Energy-Storage.news reported that Genex had agreed a AU$35 million debt finance facility for BBP from specialist project finance fund manager Infradebt under a 12-year term.

Tesla will supply 40 of its Megapack grid-scale battery storage units to the project and the US tech company’s Autobidder trading and bidding platform will control its market-facing activities. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Genex said the AU$40 million institutional placement, alongside the Infradebt loan, will go towards project construction costs as well as repay an existing debt facility to Australia’s national Clean Energy Finance Corporation and provide further working capital. 

“I am delighted to announce today the final piece for the project financing of the Bouldercombe Battery Project, being the completion of a AU$40 million institutional placement,” Genex Power CEO James Harding said, thanking the company’s existing institutional shareholders and welcoming new ones. 

“In acknowledgement of this support, I am pleased to confirm the launch of a AU$10 million Share Purchase Plan to allow our retail shareholders to participate in the capital raising on similar terms to investors under the institutional placement.”

Bouldercombe, along with Genex’s large-scale pumped hydro energy storage (PHES) plant under construction at Kidston, also in Queensland, “will add significant upside exposure for shareholders when it commences operation,” scheduled for mid-2023, Harding said. 

Read Next

May 22, 2026
Battery storage developer and operator Spearmint Energy has closed a US$450 million financing to support its 300MW/600MWh Red Egret battery energy storage system (BESS) project.
Premium
May 22, 2026
The situation and uncertainty around grid connections and grid fees in Germany is evolving, possibly enabling market participants to look beyond the August 2029 grid fee exemption cut-off date – although uncertainty is still very high.
May 21, 2026
Singapore-based Equis has launched GreenPoint Energy, a wholly owned subsidiary consolidating its Australian renewable energy and battery storage operations under a dedicated platform with a 2.5GW portfolio of 12 battery energy storage systems (BESS) and wind projects across every National Energy Market (NEM)-connected state.
May 21, 2026
Edify Energy has reached financial close on two solar-plus-storage projects in Queensland, totalling 600MW/2,400MWh of BESS.
May 21, 2026
EDP Renewables Australia has secured AU$3 million in funding from ARENA to develop the Braidwood Renewable Microgrid Project.