Edify Energy to proceed with 2,400MWh solar-plus-storage sites in Australia

LinkedIn
Twitter
Reddit
Facebook
Email

Australian developer Edify Energy has reached financial close on two solar-plus-storage projects in Queensland, Australia, featuring 600MW/2,400MWh of battery energy storage systems (BESS).

The Smoky Creek and Guthrie’s Gap solar power stations, located on the traditional lands of the Gaangalu Nation People in Banana Shire, will together deliver 720MWp of solar generation with the co-located BESS.

The projects are backed by a 20-year hybrid services agreement with mining company Rio Tinto, under which Rio Tinto will purchase 90% of the power and storage capacity to supply its Gladstone aluminium operations with lower-carbon energy.

Financial close was achieved with support from Edify’s shareholder, La Caisse (formerly CDPQ), and a syndicate of 14 domestic and international lenders.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

According to the group, the debt financing represents the first deployment under a greenfield renewable energy portfolio financing platform, a structure not previously seen in the Australian market that provides a foundation for scaling future project development.

The projects secured long-term revenue support under the Australian government’s Capacity Investment Scheme (CIS) Tender 4, which provides revenue underwriting to reduce financial risk for investors and accelerate deployment of renewable energy and dispatchable capacity.

In this tender, 20 projects were successful, with long-term contracts awarded for 6.6GW of renewable energy generation and 11.4GWh of energy storage.

As part of the CIS agreements, Edify has committed to supporting local communities and First Nations, alongside substantial local content requirements designed to benefit regional industry and suppliers.

Both projects will utilise DC-coupled hybrid configurations integrated with grid-forming inverters, technologies designed to enhance power network stability as ageing thermal generation retires.

Unlike AC-coupled systems, where solar PV and battery storage operate through separate inverters, DC-coupling enables direct current flow from solar modules to the battery energy storage system through DC/DC converters before final conversion to alternating current for grid connection.

This configuration allows the projects to capture solar energy that would otherwise be clipped at the inverter during periods of high generation, storing it for dispatch during peak demand or when solar output is low.

In an interview with our sister site, ESN Premium, last year, Neha Sinha, product manager for energy storage systems at Wärtsilä Energy Storage, discussed how DC-coupled hybrid systems address emerging market challenges and maximise system potential by improving operational flexibility and reducing capital costs through shared inverter infrastructure.

To read the full article, visit PV Tech.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.

Read Next

June 10, 2026
Gamuda Renewables has secured an interest in the 1,800MWh Hazelwood North solar-plus-storage project in Victoria, Australia.
Premium
June 9, 2026
ESN Premium speaks with Dr Thomas Sisto, of flow battery developer XL Batteries, about using LDES to combat grid strain from heatwaves and data centres.
June 9, 2026
Chinese battery manufacturer CATL will supply 2,400MWh of battery energy storage systems (BESS) for Edify Energy’s Smoky Creek and Guthrie’s Gap Solar Power Stations in central Queensland.
June 9, 2026
New Zealand’s Meridian Energy has received a draft decision proposing to ease access restrictions on contingent hydro storage at Lake Pūkaki.
June 9, 2026
Eku Energy has submitted its 1,000MWh Griffith battery energy storage system (BESS) for environmental assessment under Australia’s EPBC Act.