Cypress Creek’s first solar-plus-storage projects take off with Lockheed’s lithium

March 27, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
One of the 12 completed Cypress Creek projects, with Lockheed Martin’s energy storage solution on the right. Image: Lockheed Martin / Cypress Creek.

Cypress Creek Renewables, which developed 1GW of PV projects in an 18-month stretch up to the beginning of this year, has used Lockheed Martin’s lithium-ion battery storage solutions in a dozen just-completed solar-plus-storage projects.

Executing PV projects primarily in North Carolina and announcing US$1.5 billion of investment for 2GW of solar in that state last November, Cypress Creek used the GridStar Lithium energy storage solution made by the US aerospace and defence giant for 12 projects in communities served by Brunswick Electric Membership Corporation.

The electric cooperative has 94,390 meters in place and around 160 employees, with only around 13 consumers per mile of line, according to its figures. Adding solar-plus-storage at communities in Brunswick, Columbus, Robeson and Bladen Counties, North Carolina, will reduce peak electricity costs and create dispatchable solar resources.

Totalling 12MWh, the projects were first reported by Energy-Storage.News last summer as work began, when original developer United Renewable Energy (URE) signed PPAs with the co-op. Cypress Creek since acquired them from URE.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“This collaboration will provide significant value to our members for years to come,” CEO and general manager of Brunswick EMC corporation Don Hughes said.

Lockheed Martin began its push into stationary energy storage for grid and renewables applications in mid-2016, with company representatives telling Energy-Storage.News at the time that this marked a long-term investment in energy storage. This later included the commercial launch of flow battery products at the beginning of this year.

GridStar lithium is certified to UL 9540 product safety standards, is modular from 100kW to multi-megawatt applications and are delivered by Lockheed with batteries, controls software and balance of system components.

Despite Cypress Creek’s prolific last couple of years in PV plant development, this 12MWh tranche of projects marks the company’s first foray into solar-plus-storage, with the company undertaking development, construction, financing and commissioning.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 3, 2026
Oregon-based utility company Portland General Electric has finalised agreements for more than 1,000MW of new renewable energy and BESS projects.
March 3, 2026
The Governing Board of the Puerto Rico Electric Power Authority (PREPA) has approved renewables developer Polaris Renewable Energy’s battery energy storage system (BESS) standard offer (SO1) agreement.
Premium
March 3, 2026
Speaking to ESN Premium, Tom Best and Rachel Rundle of Eku Energy explore some of the key policies and drivers of Australia’s ESS market.
March 2, 2026
Zinc hybrid cathode battery and storage system maker Eos Energy reasserted its vision for 2026 and beyond in its Q4 and full-year 2025 financial results.
February 26, 2026
Energy storage developer and subsidiary of Canadian Solar, Recurrent Energy, has sold its 200MWh Fort Duncan battery energy storage system (BESS) project, located in Texas, US, to developer Hunt Energy Network.