Clearway Energy Group and AIP strike US$200 million equity deal for Texas BESS

LinkedIn
Twitter
Reddit
Facebook
Email

AIP Management has agreed to acquire an equity stake from Clearway Energy Group, in Pine Forest, a 300MWac solar PV and 200MW/400MWh battery energy storage system (BESS) project in Texas, US.

The investor announced its agreement to acquire a 49.99% equity stake in Pine Forest from IPP Clear Energy Group on 1 April. AIP says the total investment is approximately US$200 million.

Pine Forest is located in the Electric Reliability Council of Texas (ERCOT) North market, near to Dallas, Texas and Fort Worth, Texas transmission networks.

The project is under construction, with an expected commercial operation date (COD) of late Q4 2025.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Clearway will provide operations and maintenance oversight and asset management services, retaining a 50.01% equity stake in Pine Forest.

AIP says the solar PV capacity of the project will be fully contracted through long-term virtual power purchase agreements (PPAs) with corporate offtakers.

The BESS portion of the project will be used to participate in ERCOT’s wholesale energy and ancillary services market.

AIP is a renewable energy investment firm with global operations, majority-owned by Nordic financial group Storebrand. The company claims to have invested in approximately 7GW of renewable energy assets.

The investment firm owns two projects in California with Global Atlantic Financial Group, which in 2021 saw Mitsubishi Power Americas and Powin Energy appointed to retrofit 640MWh of batteries.

AIP has shared equity with Clearway in other BESS projects as well, including the 186MW/744MWh Lorax BESS in Riverside County, California.

Clearway owns 40% of that project, with AIP taking the majority, 60%. The project is similarly co-located with solar PV facilities. The PV facilities appear to be operational and AIP’s website says that the BESS was expected to reach commercial operation in 2024, but there does not appear to be an update on the project’s progress.

Also, in California, AIP owns 49% of the 160MW/640MWh Zion BESS projects located in Kern and Fresno County. Southern Power owns 51% of the projects.

As reported by Energy-Storage.news at the time, Southern Power turned the projects online in March 2022.

At that time, it was also announced that both systems had a PPA with Southern California Edison (SCE).

According to Clearway’s website, the company has 3 standalone utility-scale BESS projects.

This includes the 113.5MW Daggett BESS in San Bernadino County, California and the 147MW Rosamund Central BESS in Kern County, California.

The most recent update came in March when Clearway started construction on its 1,280MWh Honeycomb BESS portfolio in Utah.

In all, the company claims its portfolio is comprised of approximately 11.8GW of generating capacity across 26 states.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 25, 2026
Recently, US BESS companies Energy Vault and Goshe, SMT Energy and Climate Adaptive Infrastructure, and NeoVolta and SK On have made major deals and secured strategic partnerships.
September 24, 2026
Market research firm Wood Mackenzie stated that data centre buildout is uplifting the US battery energy storage system (BESS) outlook across all segments.
September 24, 2026
IPP Greenvolt Power has started building its Siedlce battery storage project in Poland, while Gore Street, Taaleri Energia and DS1 have moved to construction on projects in Poland, Estonia and Lithuania respectively. 
September 24, 2026
AGL has advanced two grid-scale BESS in New South Wales, one now before Australia’s EPBC Act and the other still in early planning.
September 23, 2026
Energy-Storage.news speaks with Nathan Picarsic, co-founder of Horizon Advisory, at the 2026 US Battery Asset Management and Solar and Storage Finance Summits in Garden Grove, California.