Centrica celebrates completion of 49MW battery project in England

December 20, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
Image: Centrica.

Centrica has formally announced the completion of its 49MW Roosecote battery storage project, 18 months after construction started.

The energy major said construction of the project, one of Europe’s largest battery storage facilities, started in March 2017 and had now been fully unwrapped, just in time for Christmas.

The 49MW project is able to provide sub-second respond to fluctuations in demand and was among the 500MW of battery storage projects to have received a 15-year Capacity Market contract in December 2016 for the 2020/21 winter period.

Mark Futyan, distributed power systems director at Centrica Business Solutions, said: “The Roosecote site is truly unique, having been home to the latest technology of its time and is an exemplar of the transition we’ve made from dirty coal to cleaner, more flexible power. Christmas has indeed come early for our team!”

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The site in Cumbria used to be home to a coal-fired power station that was later replaced by the country’s first combined cycle gas turbine.

It forms part of a £180 million (US$227.92 million) investment in flexible power on the part of Centrica, comprising a refurbishment and addition of a new gas turbine at the company’s King’s Lynn power station and two fast response gas-fired power stations.

Read Next

November 21, 2025
In a major week for European BESS deal-making, project acquisition and financing deals have been done in the Poland, Germany, Finland, the UK and Romania for grid-scale projects totalling well over 1GW of capacity.
November 18, 2025
The low level of the MACSE tariffs in Italy took everyone by surprise and will require careful asset management, but their relative value and those of the capacity market (CM) should increase over time. 
November 14, 2025
BESS and flexible generation provider Statera Energy has secured £235 million (US$309 million) in debt financing for its 680MW/1,360MWh Carrington BESS project in Manchester, UK.
Premium
November 7, 2025
UK BESS projects totalling nearly 4GWh awarded planning consent in October, there is now nearly 22GWh under construction.
November 7, 2025
Trina Storage has signed a memorandum of understanding (MoU) with Pacific Green Energy Group to supply up to 5GWh of battery energy storage systems between 2026 and 2028.