Australian gold mine goes 50% renewable-powered with addition of battery storage

LinkedIn
Twitter
Reddit
Facebook
Email
Wind turbines at the site, which is thought to be the first Australian mine to use wind power. Image: EDL.

A lithium-ion battery energy storage system (BESS) supplied by French manufacturer and system integrator Saft has enabled a gold mine in Australia to meet more than 50% of its energy demand with renewable energy.

Power station operating company EDL has implemented what is already thought to be Australia’s biggest microgrid operating on hybrid renewable sources – combining wind and solar – along with gas / diesel engines for backup. The system has a combined capacity of 56MW including 13MW of battery storage and is at Agnew Gold Mine, Western Australia, owned and operated by mining company Gold Fields.

Gold Fields contracted EDL to provide the 600 square kilometre mine site’s power solution through a 10-year agreement. While it allows the site to run on 50% renewables on average, at times it can deliver up to 85% of the site’s power requirements with wind and solar, EDL chief executive James Harman said. The project was completed in May. About 10% of its total cost of around AU$110 million (US$80 million) was funded through a grant from the government-backed Australian Renewable Energy Agency (ARENA).

The 13MW / 4MWh battery storage system, based on six containerised Saft Intensium Max+ 20M megawatt-scale battery storage units allows EDL’s microgrid to integrate variable renewable energy including 4MW of solar and 18MW of wind while maintaining power quality. It is also thought to be the first Australian mine microgrid to incorporate wind power. It also uses a 21MW thermal power engine.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Housed in 20ft containers, the Intensium Max lithium-ion battery systems sit alongside three containers twice as long that house its power conversion system (PCS), transform and MV switchgear. In addition to maintaining the power quality to the mine as it feeds in renewable power from variable sources the battery system will also provide spinning reserves to maintain the microgrid’s stability, minimising the need for idling fossil fuel generators to stay running.

Saft said in a press release that the battery storage, fitted out and tested at the company’s Jacksonville, Florida manufacturing hub, is designed to withstand the difficult desert conditions at the site, including temperatures which can reach 48 degrees Centigrade (118.4 Fahrenheit).

Mines have been seen as a low-hanging fruit opportunity for solar, wind and battery hybrid microgrids, given the fairly intensive energy demands of sites are often coupled with them being a long distance from reliable grid power. This means that, like islands, polluting and expensive fossil fuels need to be transported in, again, often over long distances. In February, Rio Tinto said it will tender for 34MW of solar and 12MWh of storage solutions for one of its mining sites, also in Western Australia, while 17MW / 15MWh of battery energy storage is being built alongside a 30MW solar PV plant at a gold mine in Mali, Africa, to give just two recent examples.

Battery storage systems in the foreground and solar panels behind them at the Agnew Gold Mine. Image: EDL.

Read Next

June 26, 2026
IPP Enlight Renewable Energy has announced that its US subsidiary Clēnera Holdings has entered into a debt financing framework agreement for the CO Bar Complex in Arizona, US.
Premium
June 25, 2026
ESN Premium speaks with Nextpower CEO Dan Shugar and Prevalon’s Tom Cornell about the solar PV solutions company’s (re)entry into the energy storage space.
June 25, 2026
AEMO has set out a storage requirement of almost 50GW in its latest 2026 Integrated System Plan (ISP), split between 35GW of short and medium-duration battery storage for daily firming and 5GW of long-duration energy storage (LDES) for seasonal reliability.
June 24, 2026
The Australian government has announced the results of Capacity Investment Scheme (CIS) Tender 8, selecting 15 battery energy storage projects across the National Electricity Market (NEM), totalling 4.2GW/16.1GWh.
June 23, 2026
Renewables developer rPlus Energies has announced start of commercial operations for the 400MW/1,600MWh Green River Energy Centre in Emery County, Utah, US.