Wirsol and Edify connect 60MW solar farm in Victoria, storage retrofit imminent

LinkedIn
Twitter
Reddit
Facebook
Email

Edify Energy and Wirsol Energy have connected the 60MW Gannawarra Solar Farm in northwest Victoria to the grid, with a storage retrofit expected before the summer.

The solar farm is connected on site to Powercor’s 66kV distribution line between Swan Hill and Kerang, providing access to Victoria’s power grid. The commissioning process has commenced and once in full production it will provide power to around 18,100 Victorian households.

The solar farm, which is spread over 132 hectares, will be integrated with the Gannawarra Energy Storage System – a 25MW / 50MWh Tesla Powerpack battery – developed by Edify Energy and owned jointly by Wirsol Energy and Edify Energy. The project will therefore demonstrate how existing PV projects can be successfully retrofitted with battery storage.

This element of the project is expected to be completed before the summer this year, at which time the Gannawarra Energy Storage System and the Gannawarra Solar Farm will be amongst the largest integrated solar and storage facilities in the world. This project also features a first-of-its-kind long-term commercial services agreement with the utility EnergyAustralia, who will operate the battery in conjunction with its offtake from the Gannawarra Solar Farm.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Mark Hogan, managing director of Wirsol Energy, said: “The Gannawarra solar farm is in every respect a world leading project and is testament to the future role of solar in enhancing energy supply across Australia.”

Read Next

August 4, 2026
IPP Prosalia has commissioned a 15MW/60MWh battery storage system at a solar PV plant in Portugal, while power group EDP has added one to a hybrid wind and solar project in Spain.
Premium
August 4, 2026
ESN Premium speaks with Fluence’s Jeff Monday and Sam Markham on the opportunity battery energy storage could provide data centres in Australia.
August 4, 2026
Habitat Energy has been appointed by Octopus Australia to provide optimisation services for two DC-coupled solar-plus-storage sites.
August 3, 2026
BESS and solar have driven Australia past the halfway mark in NEM renewable penetration, but the technology mix is not yet broad enough.
July 31, 2026
1414 Degrees has signed a deal to develop up to 1GW of AI data centre infrastructure at its Aurora Energy Precinct in South Australia.