UK’s Pivot Power brings online 5MWh flow battery at ‘world’s largest hybrid project’

By Alice Grundy
December 20, 2021
LinkedIn
Twitter
Reddit
Facebook
Email
Invinity’s vanadium flow battery tech at the site, where a 50MWh lithium-ion battery storage system has been in operation for a few months already. Image: Invinity Energy Systems.

Flow battery company Invinity Energy Systems, alongside developer Pivot Power, has fully energised the UK’s largest flow battery, located in Oxford, England.

It forms part of the £41 million (US$54.2 million) Energy Superhub Oxford (ESO) project, which is set to support the city’s goal of being zero carbon by 2040 or earlier, by integrating rapid electric vehicle (EV) charging, hybrid battery storage, low carbon heating and smart energy management technologies.

As such, the 5MWh flow battery will combine with a 50MWh Wärtsilä lithium-ion battery energy storage system (BESS) to operate as a single energy storage asset, with the lithium-ion component actived in June.

This will make it not only will the largest directly-transmission-connected battery installed in the UK to date, but also the largest vanadium flow and lithium-ion hybrid battery ever deployed, Invinity said.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

This hybrid approach to energy storage is designed to leverage the strengths of each technology in order to increase grid resiliency and create a smarter, more flexible energy system. 

In the ESO hybrid energy storage system, Invinity’s vanadium flow batteries are used to ‘front-end’ the energy asset, acting as a first line of response when the system is called into service. This means that the lithium-ion battery will only get called into service after the required response exceeds the capacity of the Invinity battery.

The Invinity flow battery therefore performs much of the ‘heavy-lifting’ while reducing the wear on the lithium-ion battery, with the flow battery not degrading with use, meaning it can cycle indefinitely.

“Energising the largest flow battery in the UK marks a proud moment for Invinity, but even more important is how this innovative project is a model for cities worldwide,” Larry Zulch, chief executive officer at Invinity said.

“It demonstrates that energy storage pioneers such as Pivot Power can collaborate with local government to deliver a future-proofed, flexible grid that supports the renewable energy transition and the shift to an electrified, net zero future.”

Late last month, work began on the EV charging hub element of the project, with this lauded as the UK’s largest. The site is to see the installation of 10 Fastned chargers with up to 300kW of power, 16 Gamma Energy chargers with between 7-22kW of power and 12 250kW Tesla Superchargers.

Two other Superhubs, both located in the West Midlands, are now also in the works, with Pivot Power having continued its partnership with Wärtsilä. The two are to develop 100MW/200MWh of battery storage split across the sites.

This story first appeared on Current±.

24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!
9 June 2026
Stuttgart, Germany
Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.

Read Next

December 11, 2025
A trio of large-scale BESS announcements by major power firms of 700-800MWh capacity each in Germany show the country’s energy storage market moving into the new era of scale.
Premium
December 10, 2025
Last month was the first time since June that both pre-application submissions and full planning consent submissions for grid-scale UK BESS surpassed 1GWh – just before NESO announced the results of its grid connection queue reshuffle.
December 9, 2025
The UK’s National Energy System Operator (NESO) will offer grid connection offers up to 2035 to 283GW of projects following a reform of the process.
December 9, 2025
European energy independence is achievable if long-duration energy storage is factored into the mix, writes Oonagh O’Grady of Hydrostor.
Premium
December 9, 2025
A Western Australian government initiative to deploy the largest vanadium redox flow battery (VRFB) project outside China is a “pivotal moment,” one technology provider has said.