UK regulator Ofgem to consult on de-rating DSR energy storage in 2019

LinkedIn
Twitter
Reddit
Facebook
Email
Ofgem is the UK’s regulator for electricity and gas in monopoly markets. Image:

UK energy regulator Ofgem is to consider Scottish Power’s proposal to create demand side response (DSR) technology classes intended to apply new de-rating factors to energy storage used as part of DSR bids into the Capacity Market in 2019.

The utility submitted the proposal last month to create DSR technology classes with different minimum durations, and apply the extended performance testing to these newly created groups. The Capacity Market is the UK’s mechanism by which generators are paid to guarantee energy will be available in times of network stress events, particularly in winter.

Among these would be a ‘Storage DSR’ class, which transmission system operator National Grid’s electricity market reform delivery body would be obligated to consult on applying the lower de-rating factors to.

The proposal drew the ire of aggregators and other DSR providers, who claimed Scottish Power has ‘vested interests’ in pumped storage and skewing the Capacity Market towards a support mechanism for traditional generation.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

It was submitted as part of a call for proposals issued by Ofgem last year, which closed in October. The regulator received an “unprecedented” 112 proposals from stakeholders and delivery partners, proposing to take forward 38 of them in time for the upcoming 2018 consultation round.

Our UK sister site Clean Energy News understands that Scottish Power’s proposal was received too late to be considered this year, however Ofgem intends to consult on a decision in the next round of rule change proposals in 2019.

At the same time, Ofgem rejected E.On’s proposal to revoke the government’s decision to break down the storage technology class into multiple categories, paving the way for duration-based de-rating.

It rejected a proposal from ClientEarth that would have allowed all types of CMU (Capacity Market Unit) to bid for capacity agreements of up to at least 3, and potentially 15, delivery years.

Despite the technology neutral intentions of the Capacity Market, DSR is only able to bid for one-year contracts compared to the longest contracts available to other technologies.

Instead, a number of proposals are to be taken forward and will likely impact bidders across the energy sector angling for a contract in the next Capacity Market auctions, such as:

  • An EDF proposal to amend the excess capacity volume for T-1 Auctions (currently set at 100MW) to bring it in line with the T-4 (1GW).
  • RWE’s proposal to allow New Build CMUs to use a letter from a private network owner to prequalify for a T-1 Auction.
  • A proposal from UK Power Reserve to allow capacity providers of distribution-connected CMUs to aggregate CMRS (central meter registration service) CMUs as part of a CMU Portfolio for the purposes of satisfactory performance days.
  • Welsh Power’s proposal to allow recently commissioned, non-contracted, existing CMUs to register for secondary trading once the plant has proven its ability to deliver capacity.

Read Next

Premium
August 27, 2025
We catch up with the CEO of BESS developer Harmony Energy about its strategy and plans going forward, following the sale of its affiliated Harmony Energy Income Trust (HEIT).
August 26, 2025
IPP Neoen has enlisted BESS supplier NHOA Energy for its first energy storage project in Italy.
August 26, 2025
After an initial rush to deploy that gave CAISO and ERCOT the lead in US BESS adoption, both markets are focused on capacity and availability, writes Amit Mathrani of Rabobank Americas.
August 21, 2025
Statera Energy has begun operating the biggest BESS project in the UK, connected to a National Grid substation that formerly supported two coal power plants.
Premium
August 20, 2025
Long-term BESS offtake and PPA deals are clearly on the rise in Europe, but how are they evolving vi-a-vis structures, tenors and regional differences?

Most Popular

Email Newsletter