Southern California Edison procuring distributed storage technology in Santa Barbara

LinkedIn
Twitter
Reddit
Facebook
Email
Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation. credit: SCE
Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation. credit: SCE

US utility Southern California Edison (SCE) is looking to acquire distributed energy projects to help strengthen the grid in the Goleta area of Santa Barbara, California.

SCE issued the Request for Offers (RFO) for various technologies including fuel cells, solar PV combined with energy storage, combined heat and power, standalone energy storage and other distributed generation renewables. The utility is also looking for specific applications of these technologies such as demand response and permanent load shift.

Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation, with a project completion deadline of 1 June 2020.

Eligible projects will participate in a competitive bidding process with a bidder’s conference to be held on 22 March this year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Colin Cushnie, SCE vice president of energy procurement and management, said: “Unlike other solicitations looking to increase capacity of the overall electric system, this solicitation is specifically designed to help increase resiliency for the Santa Barbara-Goleta area. We are seeking to provide our customers with increased reliability in the event of transmission outages that could affect this region, and do so with local resources.”

Read Next

September 5, 2025
Energy-Storage.news proudly presents our sponsored webinar with Qcells + Geli, on modelling and realising maximum profits from commercial & industrial (C&I) battery storage systems.
September 3, 2025
During the morning of 30 August 2025, the California Department of Forestry and Fire Protection (CAL FIRE) responded to a possible vegetation fire in the area of independent power producer (IPP) Arevon Energy’s California Flats solar-plus-storage project.
September 2, 2025
Energy-Storage.news speaks with Karina Hershberg, Associate Principal at engineering firm PAE Engineers, on integrating microgrids with sustainable building design.
Premium
August 28, 2025
Energy-Storage.news Premium speaks with Sergio Melendez, storage sector manager at CAISO, and Ali Karimian, market optimisation director at GridBeyond, about regulating Bid Cost Recovery Payments in the California Independent System Operator market.
August 28, 2025
California utility Pacific Gas and Electric (PG&E) has pushed back recommissioning of the Elkhorn battery energy storage system (BESS) by approximately one year, to 30 June 2026.

Most Popular

Email Newsletter