Southern California Edison procuring distributed storage technology in Santa Barbara

LinkedIn
Twitter
Reddit
Facebook
Email
Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation. credit: SCE
Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation. credit: SCE

US utility Southern California Edison (SCE) is looking to acquire distributed energy projects to help strengthen the grid in the Goleta area of Santa Barbara, California.

SCE issued the Request for Offers (RFO) for various technologies including fuel cells, solar PV combined with energy storage, combined heat and power, standalone energy storage and other distributed generation renewables. The utility is also looking for specific applications of these technologies such as demand response and permanent load shift.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation, with a project completion deadline of 1 June 2020.

Eligible projects will participate in a competitive bidding process with a bidder's conference to be held on 22 March this year.

Colin Cushnie, SCE vice president of energy procurement and management, said: “Unlike other solicitations looking to increase capacity of the overall electric system, this solicitation is specifically designed to help increase resiliency for the Santa Barbara-Goleta area. We are seeking to provide our customers with increased reliability in the event of transmission outages that could affect this region, and do so with local resources.”

Read Next

May 21, 2025
Installed battery storage capacity in California, US has grown from 771MW in 2019 to more than 15,500MW as of 31 January, 2025.
Premium
May 20, 2025
Matthew Biss examines legislative moves regarding the safe siting and deployment of battery storage in California, the biggest market by state in the US.
Premium
May 20, 2025
ESN Premium speaks with Chloe Hicks of EnergyCo about New South Wales’ Renewable Energy Zones (REZ) and its hopes for energy storage.
May 19, 2025
Engie North America has partnered with CBRE Investment Management (CBRE IM) on a 2.4GW battery energy storage system (BESS) portfolio in Texas and California, US.
May 19, 2025
Elements Green has received grid connection approval from Powerlink Queensland and the AEMO for a 1.3GWh solar-plus-BESS site in Queensland.

Most Popular

Email Newsletter