Southern California Edison procuring distributed storage technology in Santa Barbara

LinkedIn
Twitter
Reddit
Facebook
Email
Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation. credit: SCE
Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation. credit: SCE

US utility Southern California Edison (SCE) is looking to acquire distributed energy projects to help strengthen the grid in the Goleta area of Santa Barbara, California.

SCE issued the Request for Offers (RFO) for various technologies including fuel cells, solar PV combined with energy storage, combined heat and power, standalone energy storage and other distributed generation renewables. The utility is also looking for specific applications of these technologies such as demand response and permanent load shift.

Proposed technologies must be able to connect to a circuit, load or lower-level substation served by the Goleta 220/66kV substation, with a project completion deadline of 1 June 2020.

Eligible projects will participate in a competitive bidding process with a bidder’s conference to be held on 22 March this year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Colin Cushnie, SCE vice president of energy procurement and management, said: “Unlike other solicitations looking to increase capacity of the overall electric system, this solicitation is specifically designed to help increase resiliency for the Santa Barbara-Goleta area. We are seeking to provide our customers with increased reliability in the event of transmission outages that could affect this region, and do so with local resources.”

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 29, 2026
The California Energy Commission (CEC) has released over US$46 million for the state’s Distributed Electricity Backup Assets (DEBA) Programme.
October 27, 2026
India has 5.3GWh of operational battery energy storage system (BESS) capacity, with a further 185GWh of projects under development, according to Prashant Bhamu, deputy director of integrated resources planning at the Central Electricity Authority (CEA), part of the Ministry of Power.
October 23, 2026
Tech giant Google and distributed energy resource (DER) platform Voltus have announced an expanded agreement to build a 1GW virtual power plant (VPP) in the US.
October 23, 2026
German home energy storage and virtual power plant (VPP) company sonnen GmbH, sold by gas major Shell in August, has filed for insolvency.
October 20, 2026
US utility Dominion Energy plans to build 3.5GW of battery energy storage systems (BESS) over the next 20 years according to its recently filed integrated resource plan (IRP).